NEH-based heuristics for the permutation flowshop scheduling problem to minimize total tardiness

Fernández-Viagas Escudero, Víctor; Framiñán Torres, José Manuel

Abstract

Since Johnson׳s seminal paper in 1954, scheduling jobs in a permutation flowshop has been receiving the attention of hundreds of practitioners and researchers, being one of the most studied topics in the Operations Research literature. Among the different objectives that can be considered, minimising the total tardiness (i.e. the sum of the surplus of the completion time of each job over its due date) is regarded as a key objective for manufacturing companies, as it entails the fulfilment of the due dates committed to customers. Since this problem is known to be NP-hard, most research has focused on proposing approximate procedures to solve it in reasonable computation times. Particularly, several constructive heuristics have been proposed, with NEHedd being the most efficient one, serving also to provide an initial solution for more elaborate approximate procedures. In this paper, we first analyse in detail the decision problem depending on the generation of the due dates of the jobs, and discuss the similarities with different related decision problems. In addition, for the most characteristic tardiness scenario, the analysis shows that a huge number of ties appear during the construction of the solutions done by the NEHedd heuristic, and that wisely breaking the ties greatly influences the quality of the final solution. Since no tie-breaking mechanism has been designed for this heuristic up to now, we propose several mechanisms that are exhaustively tested. The results show that some of them outperform the original NEHedd by about 25% while keeping the same computational requirements.

Full text

See discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/273398783 NEH-based heuristics for the permutation flowshop scheduling problem to minimise total tardiness ArticleinComputers & Operations Research · August 2015 DOI: 10.1016/j.cor.2015.02.002 CITATIONS 33 READS 422 2 authors: Some of the authors of this publication are also working on these related projects: Collaboration strategies in de centralized supply chains with partial information sharing View project Models and algorithms for the order scheduling problems considering setup times View project Victor Fernandez-Viagas Universidad de Sevilla 34 PUBLICATIONS401 CITATIONS SEE PROFILE Jose M. Framinan Universidad de Sevilla 188 PUBLICATIONS3,125 CITATIONS SEE PROFILE All content following this page was uploaded by Victor Fernandez-Viagas on 06 November 2017. The user has requested enhancement of the downloaded file. NEH-based heuristics for the permutation flowshop scheduling problem to minimise total tardiness∗ Victor Fernandez-Viagas1† , Jose M. Framinan1 1Industrial Management, School of Engineering, University of Seville, Ave. Descubrimientos s/n, E41092 Seville, Spain, {vfernandezviagas,framinan}@us.es November 6, 2017 Abstract Since Johnson’s seminal paper in 1954, scheduling jobs in a permutation flowshop has been receiving the attention of hundreds of practitioners and researchers, being one of the most studied topics in the Operations Research literature. Among the different objectives that can be considered, minimising the total tardiness (i.e. the sum of the surplus of the completion time of each job over its due date) is regarded as a key objective for manufacturing companies, as it entails the fulfilment of the due dates committed to customers. Since this problem is known to be NP-hard, most research has focused on proposing approximate procedures to solve it in reasonable computation times. Particularly, several constructive heuristics have been proposed, with NEHedd being the most efficient one, serving also to provide an initial solution for more elaborate approximate procedures. In this paper, we first analyse in detail the decision problem depending on the generation of the due dates of the jobs, and discuss the similarities with different related decision problems. In addition, for the most characteristic tardiness scenario, the analysis shows that a huge number of ties appear during the construction of the solutions done by the NEHedd heuristic, and that wisely breaking the ties greatly influences the quality of the final solution. Since no tie-breaking mechanism has been designed for this heuristic up to now, we propose several mechanisms that are exhaustively tested. The results show that some of them outperform the original NEHedd by about 25% while keeping the same computational requirements. Keywords: Scheduling, Flowshop, Heuristics, NEH, tie-breaking mechanism,tardiness, PFSP. ∗Preprint submitted to Computers and Operations Research, http://dx.doi.org/10.1016/j.cor.2015.02.002. †Corresponding author 1 1 Introduction The Permutation Flowshop Scheduling Problem (denoted as PFSP) is one of the most studied problems in the Operations Research literature (see the reviews by Framinan et al., 2004; Ruiz and Maroto, 2005). This decision problem deals with scheduling njobs that have to be processed on mmachines in the same order and with the same job sequence on every machine. Different criteria have been considered in the literature for this decision problem (see e.g. the reviews by Framinan et al., 2005; Vallada et al., 2008; Pan and Ruiz, 2013), such as the maximum completion time among the jobs or makespan, the total flowtime (sum of completion times of all jobs), and the total tardiness (sum of the tardiness of each job). Makespan and total completion time are related to the fast processing of the products and to a balanced use of resources, both issues being of great importance in make-to-stock manufacturing scenarios. In contrast, total tardiness focuses on the satisfaction of customers and it is therefore better suited for make-to- order manufacturing scenarios as due dates play a key role (Panwalkar et al., 1982; Kim et al., 2001). Thereby, among the objectives considered for the PFSP, the total tardiness highlights a critical concern for manufacturing systems (see e.g. Raman, 1995; Panwalkar et al., 1973), since delays may lead to an increase in costs such as penalty clauses in a contract, loss of customers and/or bad reputation for other customers (Sen and Gupta, 1984). The PFSP with total tardiness minimisation objective is denoted as Fm|prmu|PTj(see e.g. Pinedo, 1995). Since the problem is known to be NP-hard, most researchers have focused on developing solution procedures (i.e. heuristics) that do not guarantee the optimality of the solution, but that can provide a (hopefully) good solution in a reasonable time interval. More specifically, several heuristics and metaheuristics have been proposed in the literature for the F m|prmu|PTj problem, such as those by e.g. Gelders and Sambandam (1978); Kim et al. (1996); Rajendran and Ziegler (2003); Framinan and Leisten (2008); Vallada and Ruiz (2010). Among them, the NEHedd heuristic (Kim, 1993) stands out since, as we will discuss later, many works employ it to obtain an initial solution. The NEHedd is an adaptation for the tardiness objective of the well-known NEH heuristic by Nawaz et al. (1983) for makespan minimisation. In the NEH heuristic, jobs are initially arranged in non ascending order of their processing times. Then, a 2 job sequence is constructed by evaluating the partial schedules originating from the initial order: Assuming a sequence already set for the first k−1jobs, kcandidate (sub)sequences are obtained by inserting job kin the kpossible slots of the current sequence. Out of these k(sub)sequences, the one yielding the minimum makespan is kept as the relative (sub)sequence for these first k jobs. Then, job k+ 1 from the initial order is considered analogously, and so on until all njobs have been sequenced. In order to reduce the computational burden of the NEH heuristic, Taillard (1990) proposed a mechanism (known as Taillard’s acceleration) to reduce the complexity of the NEH heuristic from n3·mto n2·m. The excellent performance of the NEH heuristic and its easy adaptation to similar problems have led to its application to other scheduling decisions, such as the PFSP with total completion time minimisation (see e.g. Framinan et al., 2003), denoted as Fm|prmu|PCj, or the hybrid flowshop scheduling problem (see e.g. Brah and Loo, 1999). For these problems, Taillard’s acceleration cannot be applied, but Li et al. (2009) present a mechanism that saves between 30-50% of CPU time for the Fm|prmu|PCjproblem, however without reducing its complexity. The NEHedd heuristic differs from the NEH heuristic in the starting order (jobs are arranged now according to the Earliest Due Date or EDD rule), and in the evaluation of the partial sequences (as the one with lowest total tardiness is selected). Taillard’s acceleration cannot be applied to the NEHedd, and, although Vallada and Ruiz (2010) propose a mechanism similar to that by Li et al. (2009), the complexity of the NEHedd remains O(n3·m). The extensive computational evaluation of heuristics for the Fm|prmu|PTjproblem carried out by Vallada et al. (2008) shows that NEHedd is a key constructive heuristic for the problem since, aside to being very efficient, the rest of efficient heuristics in the literature with more average CPU time employ NEHedd as an initial solution. More specifically, more than half of the state-of-the-art improvement heuristics or metaheuristics for the problem use NEHedd as a starting solution. This fact can be also seen in more recent works, such as Vallada and Ruiz (2010), or Schaller (2012). Despite the excellent performance of the NEHedd heuristic, we believe that additional improvements could be gained by further analysis of the problem under consideration. First, the tardiness minimisation problem could resemble different scheduling problems depending on the 3 due dates of the jobs for each specific instance: Intuitively, it is clear that, for an instance with due dates much greater than the sum of the processing times of its jobs, almost every schedule may yield zero total tardiness, thus turning the problem into a trivial one. Analogously, unachievable due dates for each job results in an instance for which almost every sequence yields tardiness for every job and therefore the problem resembles that of minimising flowtime. By conducting an analysis of these possible scenarios, further insights on the problem can be obtained, so the performance of the NEHedd procedure can be enhanced. More specifically, we will show in this paper that such an analysis reveals the importance of adequately addressing the high number of ties appearing in the constructive phase of the NEHedd. In order to handle these ties in an efficient way, we propose several tie-breaking mechanisms for the problem and conduct an extensive computational experiment to test their performance. The results show that one of these mechanisms (based on machine idle time) improves the original results obtained by NEHedd by roughly 25% while requiring the same CPU time. Another one (based on Taillard’s acceleration for makespan) outperforms the NEHedd by 15% while employing less CPU time. Furthermore, when using the idle timebased version of the NEHedd as starting solution for the metaheuristic by Vallada and Ruiz (2010) (which is the state-of-the-art metaheuristic for the problem), the metaheuristic improves its result for different stopping criteria. The remainder of the paper is organized as follows: in Section 2 the problem under consideration is described and analysed to derive some properties of the problem that may serve to identify the different scenarios and related decision problems. As a result, it is shown that there is a high number of ties for the instances in the most tardiness-specific scenario (i.e. that one not leading to trivial problems or to flowtime minimisation). Therefore, in Section 3, eight tiebreaking mechanisms are proposed. An extensive comparison among them and with the original NEHedd procedure are performed in Section 4. Finally, conclusions and future research lines are discussed in Section 5. 4 2 Analysis of the Problem The problem under study can be stated as follows: njobs have to be scheduled in a flowshop composed of mmachines. Each job jhas a processing time, tij, on each machine i. Considering a sequence π:= (π1, . . . πn), the processing time of the job in position j, i.e. job πj, is denoted as pij, where pij =tiπj.Cij denotes the completion time of job πjon machine i. The completion time of the last job of the sequence in the last machine, Cm,n =Cmax, is defined as the maximum completion time or makespan of the sequence. Let djbe the due date of job j, and pj=Pm i=1 pij the sum of the processing times of job jacross all machines. The tardiness (earliness) of job jis defined as Tj=max{Cmj −dj,0}(Ej=max{dj−Cmj,0}). Finally, total tardiness is defined as PTj=P∀jmax{Cmj −dj,0}. As discussed in Section 1, our problem is highly influenced by the due dates of the jobs in the specific instance. In this Section, we make an effort to gain a better understanding of the problem so the performance of existing solution procedures (most notably the NEHedd) can be enhanced. To do so, we first state two simple properties of the problem under consideration: Property 2.1. Let Ibe an instance of the F m|prmu|PTjproblem, and W M be the maximum (worst) makespan that can be obtained for I. If dj≥WM, ∀j, then each feasible sequence πis an optimal solution for I. That is, Ihas n!optimal solutions. Proof. The proof of this property is obvious: since W M is the worst makespan of the problem (i.e. WM ≥Cm,j,∀j) and each due date is greater than or equal to WM (i.e. dj≥WM ≥Cm,j, ∀j), then minimising P∀jmax{Cm,j −dj,0}is equal than minimising P∀jmax{−P, 0}= 0, where Pis a non-negative number, and hence each feasible solution is an optimal solution of the problem. Property 2.2. Let Ibe an instance of the F m|prmu|PTjproblem with dj≤Pm i=1 pij ,∀j. Then, an optimal solution for Ican be obtained by solving the corresponding Fm|prmu|PCj problem for I. Proof. pjis a lower bound of the makespan of the job j. When dj≤pj, then each completion time Cmj is greater than or equal to its due date, dj, and, hence P∀jmax{Cm,j −dj,0}= P∀j(Cm,j −dj) = P∀jCm,j −P∀jdj=P∀jCm,j +const. 5 These two properties formalise the interdependence between the due dates and processing times of an instance, and the type of optimisation problem. If the due dates are extremely tight, the problem is similar to that of flowtime minimisation according to Property 2.2 whereas extremely loose due dates lead to a trivial problem according to Property 2.1. Therefore, a problem instance can be classified along these two extreme cases. To do so, we first define for each job jthe following indicator vj: vj=dj−pj WM −pj (1) Clearly, vj≤0indicates that the due date cannot be met for job j, regardless of the position where it is scheduled. Similarly, vj≥1corresponds to the case where the completion time of job jis lower than its due date. By adequately truncating vj, we can obtain a normalised indicator for job j, i.e.: min{1; max{0; vj}} ∈ [0,1]. Then, the indicator vcan be defined as: v= n X j=1 min{1; max{0; vj}} n= n X j=1 min{WM −pj; max{0; dj−pj}} n·(WM −pj)(2) It can be shown that v∈[0,1], and that if, for a given instance, v= 0 (tight due dates), then minimising the total tardiness is equivalent to minimising the total flowtime. On the other extreme, if v= 1 (loose due dates), then any sequence is optimal. In addition to how tight/loose the due dates are, the variability of the due dates among jobs also plays an important role in the optimization problem, which is formalised using the following property: Property 2.3. The sequence πedd := πedd 1,· · · , πedd nobtained by the EDD rule, is an optimal solution of the Fm|prmu|PjTjproblem if dπedd j≥dπedd j−1+Pm i=1 piπedd j(or, equivalently, dπedd j≥ Pj k=1 Pm i=1 piπedd k), ∀j > 1, and dπedd 1≥Pm i=1 piπedd 1. Proof. Taking into account that Cm,πedd j−1+Pm i=1 piπedd jis an upper bound of Cm,πedd j, i.e. Cm,πedd j−1+ Pm i=1 piπedd j≥Cm,πedd j, the property can be easily proved recursively, as follows: Beginning with the first job of the sequence, πedd 1, and assuming that dπedd 1≥Pm i=1 piπedd 1, then Cm,πedd 1−dπedd 1≤ 6 Cm,πedd 1−Pm i=1 piπedd 1=Pm i=1 piπedd 1−Pm i=1 piπedd 1= 0, where it has been used that the completion time of the first job is equal to the sum of processing times, i.e. Cm,πedd 1=Pm i=1 piπedd 1. Hence, the first term of the objective function is zero, i.e. Cm,πedd 1−dπedd 1≤0−→ max(Cm,πedd 1−dπedd 1,0) = 0. Following with the job in second position and assuming that dπedd 2≥dπedd 1+Pm i=1 piπedd 2, where Cm,πedd 1≤dπedd 1by means of the job in the first position. Then dπedd 2≥Cm,πedd 1+Pm i=1 piπedd 2. Note that Cm,πedd 1+Pm i=1 piπedd 2is an upper bound of Cm,πedd 2and, hence dπedd 2≥Cm,πedd 1+ Pm i=1 piπedd 2≥Cm,πedd 2which implies that the completion time of the job in second position is again lower than its due date and that the second term of the objective function is again zero, i.e. Cm,πedd 2−dπedd 2≤0−→ max(Cm,πedd 2−dπedd 2,0) = 0. For the job in a position j, we assume dπedd j≥dπedd j−1+Pm i=1 piπedd j. As Cm,πedd j−1≤dπedd j−1from the previous job and Cm,πedd j−1+Pm i=1 piπedd j≤Cm,πedd j, then the completion time of the job in position jis lower than its due date as well as the jth term of the objective function is zero, i.e. Cm,πedd j−dπedd j≤0−→ max(Cm,πedd j−dπedd j,0) = 0. Taking into account the last expression, the minimisation of total tardiness can be written as max Pmax{Cm,j −dj,0}=max(0) and, hence, the EDD rule is optimal. Property 2.3 suggests that, for instances with high values of indicator v(i.e. loose due dates) and a high variability in the due dates of the jobs, the EDD rule may have a good performance, as the due dates would have a greater influence in the objective function than the completion times of the jobs. Clearly, for such instances, employing more sophisticated algorithms might not pay off. The three simple properties stated above determine three extreme cases of the total tardiness problem where good/optimal solutions can be found by any algorithm (i.e. v≈1), or by algorithms designed for different problems (i.e. by algorithms for flowtime minimisation if v≈0, or for tardiness minimisation in a single-machine if vis high and there is a high variability in the due dates). Obviously, the interest lies in finding efficient algorithms for instances in between these extreme cases. Therefore it is useful to review the different sets of instances that have been generated in the literature to check whether they adequately cover the specific tardiness minimisation case, or not. To the best of our knowledge, testbeds for the Fm|prmu|PTjproblem have been built 7 employing three different methods to generate due dates: •Gelders and Sambandam (1978) generate the due dates according to a uniform distribution drawn between the sum of processing time of the job and this sum plus an upper bound. This method for generating due dates is labelled in the following as GS. •Potts and Van Wassenhove (1982) generate the due dates using two parameters, Tand R, related to the mean and variance of the due dates, respectively, according to an uniform distribution between P·(1 −T−R/2) and P·(1 −T+R/2), where Pis a lower bound for the makespan. This method is labelled in the following as PV. •In Hasija and Rajendran (2004), due dates are generated according to (1+3·U[0,1]) Ppij. This method is denoted as HR in the following. Clearly, these methods produce instances with different values of the indicator vand, in the case of the PV method, parameter Rcontrols the variability of the due dates among jobs. To analyse the range of instances generated by each method, three different benchmarks have been built in the following manner: we consider the data regarding number of jobs, machines, and processing times as in the testbed by Vallada et al. (2008) (i.e. n={50,150,250,350}, m={10,30,50}and processing times drawn from a uniform [1,99] distribution), and generate three testbeds: •The first testbed is that by Vallada et al. (2008), which was generated using the PV procedure with parameters T={0.2,0.4,0.6}and R={0.2,0.6,1.0}, and produced 5 replicates for each combination of m,n,T, and R. In total, 540 instances were obtained. •The second testbed is generated using the GS procedure. To have the same number of instances than in the previous testbed, 45 replicates are generated for each combination of mand n. •The third testbed is generated in an analogous manner to the previous one (with 45 replicates for each combination of mand n), but using the HR procedure for due date generation. 8 3 Proposed tie-breaking mechanisms As mentioned in the previous section, no specific tie-breaking mechanism is mentioned in the original NEH heuristic for makespan minimisation. Indeed, it is cited (Nawaz et al., 1983) that ‘... Next, the job with the third highest total process time is selected and the three partial sequences are tested in which this job is placed at the beginning, middle and end of the partial sequence...’, which seems to indicate that the first position where a tie is found is selected. In the following, we will denote this tie-breaking mechanism as FT (First-Tie). Later, in the race for improving the NEH heuristic, Kalczynski and Kamburowski (2007) established the importance of breaking ties in the NEH heuristic and proposed a tie-breaking mechanism to improve the results obtained by the NEH heuristic. Since then, this aspect has been extensively analysed in the literature and several tie-breaking mechanisms have been proposed for the PFSP to minimise makespan (see Kalczynski and Kamburowski, 2008, Dong et al., 2008, Kalczynski and Kamburowski, 2009, Ribas et al., 2010, Kalczynski and Kamburowski, 2011, or Fernandez-Viagas and Framinan, 2014). To the best of our knowledge, there are no tie-breaking mechanisms proposed for the NEHedd procedure, which adopts the first-tie mechanism as in the original NEH heuristic. However, it has to be noted that, since the EDD rule sorts the jobs according to non-decreasing due dates, in case of ties in the first iterations of NEHedd, the jobs would be finally ordered according to non-increasing due dates, which would probably lead to a worse final sequence than using a different mechanism. In this section, several tie-breaking mechanisms are proposed to improve the traditional tiebreaking mechanism of the NEHedd procedure. The pseudo-code for the NEHedd algorithm including a generic tie-breaking mechanism is shown in Figure 6. The proposed tie-breaking mechanisms involve using a secondary indicator related to the performance of the partial sequence. The goal is to pick, among those slots with the same tardiness, the slot yielding the best value of the secondary indicator for the unscheduled jobs. Thereby, total idle time (IT 1or IT2, see below), total flowtime (CT)), total earliness (ET ) and makespan (MS) are chosen as potential secondary indicators. Note that, since these indicators have to be computed for every slot where the job is to be inserted in each iteration of the 15 Procedure NEHedd(TBX) α:= Jobs ordered by non-decreasing due dates where α={α1, ..., αi, ..., αn}; π:= {α1}; for k= 2 to ndo Test job αkin any possible position of π. π:= permutation obtained by inserting αkin the position of πwith less total tardiness breaking ties according to an specific mechanism; end end Figure 6: NEHedd with different tie-breaking mechanisms algorithm, they have to be carefully chosen so that the additional computational effort pays off. More specifically, the tie-breaking mechanisms analysed in this paper are: •First tie, NEHedd(TBF T ). Original tie-breaking mechanism of the NEHedd algorithm proposed in Nawaz et al. (1983) where, in case of ties, the first tie is chosen. •Last tie, NEHedd(T BLT ). This tie-breaking mechanism simply consists in selecting the last tie as reference for the next iteration. This tie-breaking mechanism tries to solve the problem of TBF T where jobs are sorted according to the reverse EDD rule. •Total idle time, NEHedd(TBIT 1)and NEHedd(TBIT 2). Denoting front delay of a machine as the time until it starts processing the first job, and back delay of a machine as the time between completing the processing of the last job and the completion of all jobs in any machine, machine idle time can be ambiguously defined by means of at least three different ways (Framinan et al., 2003), i.e.: idle time including front delays and excluding back delays (denoted as IT1); idle time excluding front and back delays (denoted as IT2); and idle time considering front delays and back delays. If we adopt the first definition of idle time, then the idle time of machine ican be calculated as IT 1i=Cin −Pn j=1 pij. Consequently, the total idle time is IT1 = Pm i=1 IT1i. Minimising IT1looks for a more compacted schedule of the inserted jobs and it is equivalent to the minimisation of the sum of the completion times of each job in each machine. On the other hand, the second definition of idle time (excluding both delays) can be calculated as IT 2 = Pn j=2 Pm i=2 max{Ci−1,j −Ci,j−1,0}. The heuristics resulting from the 16 use of these tie-breaking mechanisms in NEHedd are denoted as NEHedd(TBIT 1)and NEHedd(T BIT 2)respectively. Finally, note that the minimisation of the third definition of idle time is analogous to the minimisation of makespan and, therefore, it is considered below when discussing breaking ties according to the makespan. •Total completion time, NEHedd(TBCT ). Total completion time can be defined as follows: ct =Pj j=1 Cm,j. As with idle time, this tie-breaking mechanism tries to balance the use of resources, and the resulting NEHedd heuristic is denoted by NEHedd(TBCT ). •Total earliness, NEHedd(T BET ). If a job finishes before its due date, its earliness indicates the time between the due date and the completion time of the job. Given several sequences with the same total tardiness, sequences with a high value of the total earliness indicate that, on average, the completion times of the jobs are far from their due dates. Thus, breaking ties by maximising earliness looks for sequences with a greater buffer against the due date of each job, which tries to improve the objective function when the following jobs are inserted in any position of the sequence. NEHedd(TBET )is denoted when earliness maximisation is used in the NEHedd algorithm to break ties. •Makespan, NEHedd(T BMS). Similarly to the first two tie-breaking mechanisms, the minimisation of the makespan tries to compress the sequence for the subsequent iterations. The NEHedd heuristic using the minimisation of the makespan as tie-breaking mechanism is denoted as NEHedd(T BMS). •Makespan using Taillard’s acceleration, NEHedd(TBMS−T aillard,IT 1). As explained in Section 1, Taillard’s acceleration represents a huge reduction of the computation time of the NEH algorithm and it is one of the main reasons for its efficiency. However, it cannot be applied to total tardiness minimisation since the completion time of each job in the last machine is needed. To reduce the computation time of the NEHedd algorithm for the tardiness goal, this tie-breaking mechanism applies the NEH algorithm to minimise the makespan, using Taillard’s acceleration as long as the tardiness of the (partial) sequence is zero, i.e. in the first iterations of the algorithm when applied. Once the (partial) tardiness is greater than zero, the proposed algorithm minimises the total tardiness (without Taillard’s 17 Procedure NEHedd(T BMS−T aillard,IT ) α:= Jobs ordered by non-decreasing due dates where α={α1, ..., αi, ..., αn}; π:= {α1}; flag := true; for k= 2 to ndo if flag then π1:= π; Test job αkin any possible position of π1(using Taillard’s acceleration). π1:= permutation obtained by inserting αkin the position of π1with less makespan; TT := total tardiness of the sequence π1; if TT > 0then flag := false; else π:= π1; end end if flag 6=true then Insert job αkin the position of πwhich minimises the total tardiness breaking ties according to the total idle time IT1 of the sequence. end end end Figure 7: NEHedd(T BMS−T aillard,IT ) acceleration) breaking ties according to the total idle time, IT1. The pseudo code of this method is shown in Figure 7. •Random, NEHedd(T Brand). A random tie-breaking mechanism is proposed as a baseline for comparisons with the other mechanisms. 4 Computational Experience Each proposed tie-breaking mechanism has been compared under the same computer conditions, which means the same computer and the same programming language (C#). Algorithms were tested using the set of instances of the benchmark of Vallada et al. (2008) described in Section 2. The different tie-breaking mechanisms were compared by means of the RDI (described in Section 2) as an indicator of the quality of the solution. 18 Instance TBF T TBLT TBrand TBIT 1T BIT 2TBCT TBMK TBET TBMS−T aillard,IT 1 50x10 17.46 17.46 17.25 13.72 15.22 15.21 14.47 15.21 14.53 50x30 19.79 20.31 19.55 18.61 18.69 18.80 18.74 18.80 18.68 50x50 18.17 17.94 17.88 17.57 18.12 17.88 17.98 17.88 17.97 150x10 13.80 13.60 14.45 9.91 10.91 11.11 10.61 11.11 10.69 150x30 20.70 20.35 20.68 15.81 16.47 18.32 17.83 18.32 17.02 150x50 22.04 21.26 21.70 18.57 19.64 19.96 20.14 19.96 19.64 250x10 10.06 9.46 10.02 6.70 7.31 7.45 7.47 7.45 7.26 250x30 17.81 17.03 17.93 11.62 12.19 14.58 13.82 14.58 13.29 250x50 20.21 19.52 20.13 13.96 14.73 17.49 16.87 17.49 15.90 350x10 9.01 8.59 8.86 6.14 6.30 6.47 6.63 6.47 6.65 350x30 15.74 15.43 15.95 9.84 10.41 12.21 11.88 12.21 11.40 350x50 17.38 16.87 17.11 11.10 11.63 14.01 13.74 14.01 13.11 Average 16.85 16.48 16.79 12.80 13.47 14.46 14.18 14.46 13.84 Table 1: Relative deviation index (RDI) for the NEHedd heuristic using different tiebreaking mechanisms The results of the heuristics are shown in Table 1 in terms of their values of RDI. The best overall results are found using IT1as tie-breaking mechanism with an average RDI (denoted as ARDI) of 12.80, roughly about a 25% less than in the original FT. Note that each tiebreaking mechanism (also including the random mechanism) outperforms on average the original mechanism of the NEHedd algorithm, NEHedd(TBF T ), which has an ARDI of 16.85. Although the difference between this original tie-breaking mechanism and the NEHedd(TBLT )or the NEHedd(T Brand)is less than 0.37, for the rest of tie-breaking mechanisms the ARDI is at least a 2.39 lower than that obtained by NEHedd(TBF T ), which represents an increase in the quality of the solution without increasing the complexity of the algorithm. The CPU times of each algorithm for each combination of nand mare shown in Table 2. The differences between CPU times are negligible with the exception of the NEHedd(TBMS−T aillard,IT 1), which requires a bit less computational effort and has an ARDI of 5.63, 3.22 lower than that ofFT. Given that each tie-breaking mechanism is a version of the original NEHedd algorithm and that the same test bed for all tie-breaking mechanisms is used, it is clear that the random variables (RDI) are related and the hypothesis of independence can be rejected (see Table 3 for each comparison). However, the hypothesis of normality is not fulfilled, so a paired samples t-test cannot be used. Two non-parametric statistical hypothesis tests (Wilcoxon signed-rank 19 Instance TBF T TBLT TBrand TBIT 1T BIT 2TBCT TBMK TBET TBMS−T aillard,IT 1 50x10 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 50x30 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 50x50 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 150x10 0.43 0.42 0.43 0.42 0.42 0.44 0.42 0.43 0.40 150x30 1.29 1.29 1.29 1.30 1.30 1.30 1.29 1.30 1.27 150x50 2.16 2.16 2.16 2.18 2.18 2.17 2.15 2.16 2.15 250x10 1.92 1.90 1.91 1.89 1.89 1.96 1.90 1.95 1.77 250x30 5.86 5.84 5.86 5.85 5.84 5.94 5.85 5.92 5.67 250x50 9.92 9.91 9.95 9.96 9.97 9.99 9.89 9.94 9.78 350x10 5.15 5.14 5.15 5.08 5.07 5.26 5.12 5.24 4.73 350x30 15.86 15.85 15.89 15.80 15.76 16.10 15.85 16.03 15.23 350x50 26.99 26.98 27.06 27.01 27.01 27.26 27.05 27.18 26.35 Average 5.81 5.80 5.82 5.80 5.80 5.88 5.81 5.86 5.63 Table 2: Average CPU times for the NEHedd heuristic with different tie-breaking mechanisms Comparison N Correlation Sig. NEHedd(T BF T )vs NEHedd(TBIT 1)540 0.707 0.000 NEHedd(T BF T )vs NEHedd(TBIT 2)540 0.760 0.000 NEHedd(T BF T )vs NEHedd(TBMS−T aillard,IT 1)540 0.816 0.000 NEHedd(T BF T )vs NEHedd(TBCT )540 0.876 0.000 NEHedd(T BF T )vs NEHedd(TBMK )540 0.826 0.000 NEHedd(T BF T )vs NEHedd(TBET )540 0.876 0.000 NEHedd(T BF T )vs NEHedd(TBLT )540 0.949 0.000 NEHedd(T BF T )vs NEHedd(TBrand)540 0.962 0.000 Table 3: Analysis of dependence of samples test and sign test) are carried out then with a confidence level of 99% to compare the statistical significance between the mean and the median of the samples, respectively. Results of the tests are shown in Table 4. For both tests, each tie-breaking mechanism statistically outperforms the original one with the exception of the random tie-breaking mechanism, for which no statistical difference was found (p-values of 0.794 and 0.727 for the Wilcoxon signed-rank test and sign test respectively). Regarding the significance of the different tie-breaking mechanisms, the highest p-value found was 0.004 when comparing TBLT and TBF T , which indicates the relatively bad performance of the original tie-breaking mechanism of the NEHedd procedure. The rest of the p-values are 0.000. ARDI is shown in Table 5 grouped by the values of the different parameters in the testbed: 20 Comparison Wilcoxon signed-rank test Sign test Z Sig. Z Sig. NEHedd(T BF T )vs NEHedd(TBIT 1)-14.498 0.000 -12.363 0.000 NEHedd(T BF T )vs NEHedd(TBIT 2)-13.665 0.000 -11.446 0.000 NEHedd(T BF T )vs NEHedd(TBMS−T aillard,IT 1)-13.829 0.000 -12.020 0.000 NEHedd(T BF T )vs NEHedd(TBCT )-13.616 0.000 -13.207 0.000 NEHedd(T BF T )vs NEHedd(TBMK)-13.246 0.000 -11.810 0.000 NEHedd(T BF T )vs NEHedd(TBET )-13.616 0.000 -13.207 0.000 NEHedd(T BF T )vs NEHedd(TBLT )-3.865 0.000 -2.904 0.004 NEHedd(T BF T )vs NEHedd(TBrand)-0.262 0.794 -0.349 0.727 Table 4: Wilcoxon signed-rank test and sign test The first and second columns correspond to the value of each parameter in each row according to the values of T,R,nand mof the testbed. The third and fourth columns represent the average number of ties per iteration and the maximum number of ties in an iteration, respectively. The rest of the columns show the ARDI values for each tie-breaking mechanism. ARDI values for each tie-breaking mechanism are always lower than the ARDI of TBF T regardless of the value of the parameters, with the exception of T Brand and TBLT . Although NEHedd(TBLT )statistically outperforms NEHedd(TBF T )in the whole testbed, this does not happen when grouping by parameters. The minimum difference between the original tie-breaking mechanism and the rest is found for T= 0.6and R= 1.0, which corresponds to tighter due dates with high variance. Obviously, the performance of the tie-breaking mechanism is related to the average number of ties. Thereby, note that the average and maximum number of ties decreases as m,T, or Rincrease, or as ndecreases, reaching the maximum value of ties for the following combination of parameters: T= 0.2,R= 0.2,n= 350 and m= 10. Regarding the behaviour with respect to indicator v, CRDINEH_T B(IT 1) the difference between the best tie-breaking mechanism TBIT 1as compared to the original one is shown in Figure 8. Most points are below zero in the y-axis, which highlights the improvement achieved by the heuristic when using IT1as a tie-breaking mechanism, especially for v > 0.15 where the problem is far from being of the type F m|prmu|PCj. 21 Figure 8: CRDINEH_T B(IT 1) in each instance of the Benchmark of Vallada et al. (2008). Parameter Ties Tie-breaking mechanisms Mean Max. FT LT rand IT1 IT2 CT MK ET MS-Taillard, IT1 T0.2 22.5 210 14.57 13.91 14.47 7.18 8.27 10.45 9.71 10.45 8.90 T0.4 6.5 144 18.14 17.92 18.08 14.15 14.95 15.84 15.67 15.84 15.45 T0.6 1.1 81 17.83 17.62 17.83 17.06 17.18 17.09 17.17 17.09 17.19 R0.2 17.1 210 20.86 19.72 20.49 13.14 14.27 15.65 15.02 15.65 14.96 R0.6 8.3 146 16.83 16.70 16.84 12.88 13.60 15.00 14.84 15.00 14.07 R1 4.7 112 12.86 12.98 12.95 12.41 12.51 12.69 12.77 12.69 12.57 n50 0.5 23 18.25 18.28 17.85 16.81 17.32 17.18 17.20 17.18 17.15 n150 3.8 81 18.85 18.40 18.94 14.76 15.67 16.47 16.19 16.47 15.78 n250 8.9 153 16.03 15.33 16.02 10.76 11.41 13.17 12.72 13.17 12.15 n350 14.9 210 14.11 13.70 14.04 9.13 9.55 10.98 10.84 10.98 10.47 m10 16.0 210 12.37 12.02 12.32 9.13 9.80 9.90 9.82 9.90 9.75 m30 8.7 182 18.25 18.06 18.38 13.82 14.26 15.79 15.43 15.79 14.97 m50 5.4 162 19.30 18.78 19.04 15.16 15.86 17.20 17.05 17.20 16.52 Table 5: Average number of ties for iteration, maximum number of ties in an iteration and ARDI for each tie-breaking mechanism. 22 Stopping Criterion ARDI-GAPR Wilcoxon signed-rank test Sign test NEHedd(T BF T )NEHedd(TBIT 1)p-value p-value t= 0.514.66 11.01 0.000 0.000 t= 1 12.65 9.72 0.000 0.000 t= 2 10.61 8.42 0.000 0.000 t= 5 7.57 6.65 0.000 0.000 t= 10 6.25 5.63 0.000 0.000 t= 20 5.09 4.71 0.000 0.000 Table 6: ARDI, Wilcoxon signed-rank test and sign test for the GAPR algorithm when it is initialized with NEHedd(T BIT 1)and NEHedd(TBF T ) 4.1 Influence of the proposed tie-breaking mechanisms on iterative improvement algorithms In this section, we evaluate the influence of the proposed NEH-based heuristics when they are incorporated as seed sequences in iterative improvement algorithms. For this comparison, we use the genetic algorithm, GAPR, proposed by Vallada and Ruiz (2010). Three types of genetic algorithms were proposed. Each one was shown to be statistically more efficient than other iterative improvement algorithms in the literature for three different stopping criteria. The GAPR algorithm uses a fast selection mechanism denoted as n-tournament as well as the path relinking as crossover mechanism. As initial solution, the algorithm uses 28 random sequences and two individuals provided by the original NEHedd algorithm and by the EDD despatching rule. To analyse the influence of the chosen tie-breaking mechanism, we substitute the NEHedd seed sequence by the best proposed NEHedd-based constructive heuristic, i.e. NEHedd(T BIT 1), and we compare them using the same benchmark as in the previous Section. Average computational results in terms of ARDI are shown in Table 6 and in Figure 9 for six different stopping criteria to observe the evolution of the performance for different CPU times, t·n·(m/2) with t∈ [0.5,1,2,5,10,20] expressed in milliseconds. Obviously, one might expect that the influence of the initial solution on a well-designed metaheuristic such as the GAPR would decrease with the CPU time. Still, for the range of CPU times employed (which represents around 3 minutes of CPU times per instance for the biggest sizes), the results show that our proposal positively impacts on the quality of the solution. In fact, 23 Figure 9: Evolution of the GAPR algorithm with different initial solutions for six different stopping criteria. the positive contribution of the tie-breaking mechanism is found to be statistically significant for every stopping criteria, for both non-parametric statistical hypothesis tests (Wilcoxon signed-rank test and sign test). The highest found p-value was 0.000 (see Table 6). 5 Conclusions In this paper, several tie-breaking mechanisms for the NEH heuristics have been proposed to solve the Fm|prmu|PTjproblem. It is clear that, depending on the due dates, the decision problem to be solved is different. Extremely tight due dates induce to a Fm|prmu|PCjproblem, whereas very loose due dates lead to a trivial problem. Thereby, the problem has been first analysed in detail, depicting the limits between the tardiness problem and other problems. As a conclusion, it was obtained that several testbeds generate instances for a problem more similar to Fm|prmu|PCj. Additionally, it has been found that the number of ties in each iteration of the NEHedd heuristic is very high outside these limits (i.e. the most interesting setting regarding tardiness minimisation), and that the original tie-breaking mechanism of NEHedd would result in worse sequences as it orders the jobs in non-increasing due dates in the very likely case of ties in the first iterations. To address this problem and to enhance the performance of the 24