Using real-time information to reschedule jobs in a flowshop with variable processing times January 23, 2019 Abstract In a time where detailed, instantaneous and accurate information on shop-floor status is becoming available in many manufacturing companies due to Information Technologies initiatives such as Smart Factory or Industry 4.0, a question arises regarding when and how this data can be used to improve scheduling decisions. While it is acknowledged that a continuous rescheduling based on the updated information may be beneficial as it serves to adapt the schedule to unplanned events, this rather general intuition has not been supported by a thorough experimentation, particularly for multi-stage manufacturing systems where such continuous rescheduling may introduce a high degree of nervousness in the system and deteriorates its performance. In order to study this research problem, in this paper we investigate how real-time information on the completion times of the jobs in a flowshop with variable processing times can be used to reschedule the jobs. In an exhaustive computational experience, we show that rescheduling policies pay off as long as the variability of the processing times is not very high, and only if the initially generated schedule is of good quality. Furthermore, we propose several rescheduling policies to improve the performance of continuous rescheduling while greatly reducing the frequency of rescheduling. One of these policies, based on the concept of critical path of a flowshop, outperforms the rest of policies for a wide range of scenarios. Keywords: Rescheduling, Flowshop, Industry 4.0, Variable Processing Times, Critical Path 1
1 Introduction Recent developments in Industrial Informatics and Information and Communications Technology –such as Industry 4.0– seem to anticipate a situation in which the shop floor status in many manufacturing companies is instantly available (Chen et al., 2016). The potential challenges and advantages of using this real-time data in production management have been discussed in different contributions, such as e.g. Waschneck et al. (2017). In this paper, we intend to focus on the potential of using such real-time information to improve scheduling decisions in a manufacturing scenario where the processing times of the jobs are subject to variability. More specifically, we wish to assess the advantages of using information about the jobs already processed in some machines to reschedule the subsequent jobs yet in a permutation flowshop where the processing times are not deterministic. The choice of the flowshop environment is motivated by the enormous attention that this layout has attracted from both academia and practice due to its challenging theoretical complexities and wide applications in assembly/manufacturing industries, as well as in medical operations (see e.g. Liu et al., 2017a for a recent recollection of flowshop scheduling applications, and Fernandez-Viagas et al., 2017 for a recent review of the scientific literature). We consider the makespan as an indicator of the performance of system, as it is undoubtedly the most common objective for flowshop scheduling in general and specifically for the study of this problem under uncertainty (Gonz´alez-Neira et al., 2017). Despite this interest, the literature on rescheduling in the flowshop setting is rather scarce as compared to rescheduling in other layouts. Even the analysis of rescheduling literature in other layouts does not shed too much light on the subject of our research: In general, it is acknowledged that the performance of the system is related to the frequency of rescheduling, which seems intuitive as the schedule is continuously modified to take into account events that could not have been foreseen at the time the initial schedule was developed. However, these rather general results are obtained for the case where an infinite arrival of jobs is considered and it has to be noted that, in a permutation flowshop setting, all jobs must follow the same route across all machines, so once a job enters into the shop floor (i.e. in the first machine), then it should be processed according to the same sequence in the rest of the machines. Since the sequence of the jobs already in the shop cannot change, the only 2
point in time where the shop floor information can be used is when a job has completed its processing on the first machine, leaving this machine free for the subsequent jobs. In these circumstances, it is not clear under which conditions rescheduling pays off: First, the permutation constraint limits the number of choices (and potential advantages) for rescheduling. Second, although more data are known, the rescheduling procedure has to rely on estimates of the completion times of the jobs already in the shop, therefore some procedures to estimate such completion times and to perform an efficient rescheduling –usually time consuming– have to be provided. More specifically, in this paper we address the following two (interrelated) research questions: 1. Are there scenarios where it is advantageous to use real-time information on the (actual) completion times of the jobs already in the shop to reschedule the remaining jobs so the performance of the system is improved? What are the main features of these scenarios? 2. In those scenarios, how rescheduling should be performed? I.e. Which are the most efficient methods to generate an initial schedule and to reschedule? Note that the answers to these research questions have important implications for schedulers, as they greatly influence the approach to schedule jobs in flowshops subject to processing times variability. In the subsequent experimentation carried out in the paper, we will show, with respect to 1), that there are advantages in resequencing using the available information if the variability of processing times is low or medium (i.e. a coefficient of variation of the processing times between 0.5 and 1.0 in our experiments). These advantages blur for scenarios where the variability of the processing times is high (i.e. a coefficient of variation of 1.5). Furthermore, we will show that the quality of the initial schedule is critical to achieve such superior performance, so resequencing an initial schedule of poor quality does not lead to a good system’s performance. Regarding 2), we propose several event-driven rescheduling policies that compare favourably to a continuous rescheduling policy while being much less time consuming. Most notably, triggering the rescheduling procedure based on the disruption of the critical path of the base schedule provides excellent results in terms of performance and of rescheduling requirements. The remainder of the paper is as follows: Section 2 presents the problem background and discusses the related literature, while in Section 3 we formalise our problem and introduce the 3
required notation. In Section 4 we present different strategies that can be adopted to carry out the resequencing process. The computational experience is described in Section 5 together with the main results, while in Section 6 we present the conclusions of our work and point out future research lines. 2 Background In actual manufacturing systems, production is a highly dynamic process subject to different unexpected events and requirements (Hao and Lin, 2010). Therefore, shop floor managers must consider different strategies, policies and methods to cope with this changing environment. The classical paper by Vieira et al. (2003) describes a general framework to classify such strategies, policies and methods and, in the following discussion of the related literature, we basically adopt their framework, although we further differentiate some sub-categories to make explicit some the options. More specifically, we consider that there are two main approaches for shop floor scheduling in dynamic environments (Church and Uzsoy, 1992), i.e. dispatching rules, or schedule generation. Under the approach of dispatching rules, whenever a machine becomes free, a priority rule is employed to decide what job to process next. This approach is also known as a completely reactive approach (Aytug et al., 2005). Dispatching rules are usually fast and can be implemented easily, which constitutes a great advantage. However, there is empirical evidence that for complex systems with high competition for resources, the schedule generation approach has the potential to significantly outperform dispatching rules (see e.g. Ovacik and Uzsoy, 1994). Furthermore, in our specific case, the constraint regarding the permutation of the jobs across the machines greatly limits the potential of using dispatching rules. Under the schedule generation approach, a schedule is developed so the starting times of each job on each machine is determined in advance. Since different unforeseen events may take place, two different strategies can be adopted: •To maintain the initial schedule —also labelled base schedule–, other than a time shifting in the Gantt chart (i.e. right-shifting or left-shifting the starting times of the jobs to delay or advance the schedule but without changing the relative order of the operations). This option 4
is also labelled as fixed sequencing (Sabuncuoglu and Kizilisik, 2003). Clearly, the suitability of this option depends on how the initial schedule has been generated and the nature of the unforeseen events. If the schedule has been generated assuming a deterministic scheduling setting, it is likely that the performance of the initial schedule is substantially worsened with respect to the initial results expected. Another possibility is to develop a schedule which explicitly considers the probability of unforeseen events when generating the initial schedule, usually by minimizing the expected value of the objective function(s), i.e. to use stochastic scheduling techniques to develop the base schedule. Finally, a third alternative would be to employ (deterministic) robust scheduling in order to produce an initial schedule which is rather insensitive to the unexpected events, i.e. the potential performance of the initial schedule is sacrificed so a schedule is generated in order that its expected behaviour is not too much degraded in front of unforeseen events. •To reschedule, i.e. to modify the scheduling in view of the new data available. This approach is labelled as scheduling/rescheduling (Sabuncuoglu and Kizilisik, 2003) or proactive-reactive (Aytug et al., 2005), and it is the most commonly used method under uncertainty (Liu et al., 2017b). The main decision in this case is to decide when the rescheduling process is triggered (i.e. the so-called rescheduling policy). Different types of rescheduling policies may be adopted (Church and Uzsoy, 1992): –Continuous rescheduling (CR). Rescheduling is performed every time an event that is recognised by the system (such as the arrival of new jobs, machine breakdown, or the completion time of a job), occurs. –Periodic rescheduling (PR). Rescheduling is performed periodically in given time intervals –named rescheduling points–, which have been fixed in advance. The events occurring between rescheduling points are ignored until the following rescheduling point. –Event-driven rescheduling (EDR). Rescheduling is triggered upon the fulfilment of certain conditions related to the status of the shop floor. Note that both CR and PR can be seen as a particular case of EDR (indeed this is the case in the framework by Vieira et al., 2003), nevertheless we wish to explicitly differentiate these options as it is also 5
customary in the related literature (see e.g. Aytug et al., 2005). In addition, it is commonplace to classify the manufacturing environment where the above scheduling decisions take place either as static (the number of jobs to be scheduled is finite), or dynamic (the number of jobs to be scheduled is assumed infinite), see Vieira et al. (2003). Equipped with the above framework, we can classify the related literature on the flowshop layout. Apart from several work dealing with dispatching rules (see e.g. El-Bouri, 2012, El Bouri and Amin, 2015 and Heger et al., 2016), several contributions can be noted with respect to rescheduling approaches. Akturk and Gorgulu (1999) suggest a strategy by which, after machine failure, part of the initial schedule is rescheduled to match up with the original schedule at some point in time. Since rescheduling takes place after each machine failure, their approach can be considered a CR policy. Swaminathan et al. (2007) address the problem of flowshop scheduling where new jobs arrive over time using a CR policy. They study the differences between enforcing the use of permutation schedules or not. Their results conclude that there may be significant gains in performance when the permutation requirement is relaxed. The paper by Katragjini et al. (2013) addresses rescheduling in a dynamic permutation flowshop with different types of disruptions –random job arrivals, machine breakdowns, and job ready time variations–, and presents a metaheuristic to continuously reschedule the jobs with the two objectives of system performance and schedule stability. Rahman et al. (2013) presents the order acceptance problem in a dynamic permutation flowshop subject to random job arrivals. If the newly arrived job is accepted, then it can be scheduled using a right-shifting strategy, or by conducting a reschedule using a memetic algorithm. The results conclude that rescheduling using a memetic algorithm produces a lower makespan. Their approach also uses a CR policy. Rahmani and Heydari (2014) address the problem of schedule generation and rescheduling in a dynamic flowshop with variability of the processing times and random job arrivals. The schedule generation is aimed to obtain a robust solution whereas a multi-objective linear programming model (with makespan, schedule stability and robustness as objectives) is used to perform a continuous rescheduling. The procedure is favourably compared against other heuristics. Liu et al. (2016) study a permutation flowshop with sequence dependent setup times and different types of disruption events (including processing time variation). They use a multi-objective metaheuristic to conduct a CR policy in order to obtain a Pareto set of indicators of system’s performance and deviation 6
from initial schedule, which is obtained using a deterministic hybrid Genetic Algorithm. Liu et al. (2017a) address the problem of scheduling a flowshop with machine breakdowns and unexpected job arrivals under a predictive-reactive approach using CR. The rescheduling procedure aims at considering simultaneously the robustness of the schedule, and customer and users satisfaction. Finally, Liu et al. (2017b) address the problem of rescheduling a new order (consisting of many jobs) arriving to a dynamic permutation flowshop where the objective is to minimise the makespan of the new jobs while not violating the due date of the set of old jobs. Different CR policies mixing new and old jobs while satisfying the problem constraints are tested. As it can be seen from the review of the related literature, although rescheduling in permutation flowshops has been addressed in several contributions, none of the references focuses on the research questions posed in Section 1. More specifically, it can be seen that there is no study assessing the potential advantages of rescheduling as compared with not to perform it. Despite its intuitive advantages, there is also a substantial body on contradictory research that discourages frequent replanning and scheduling in many shop floor layouts (see e.g. the review by Hozak and Hill, 2009), therefore this issue should be properly assessed. Furthermore, most of the studies assume a dynamic flowshop. Finally, regarding the different rescheduling procedures and policies, it can be seen that the most common policy is to perform CR and to reschedule using sophisticated approximate methods. However, this renders the rescheduling process extremely time consuming so it may not be feasible from a practical point of view (Pfeiffer et al., 2007). Therefore, it is of interest to investigate whether there are other, less CPU-intensive, efficient policies and procedures. To address these issues, first we formulate the problem under consideration in order to develop the computational experience, while in Section 4 we discuss the different rescheduling policies and procedures that can be considered. 3 Problem statement In the deterministic permutation flowshop scheduling problem, there are njobs to be processed sequentially on a set of mmachines. The permutation constraint indicates that the sequence of the jobs is the same for all machines. Additionally, it is usually assumed that machines are always 7
available, and that there are no setup times. For a complete list of the assumptions in the classical permutation flowshop problem, see e.g. Framinan et al. (2014). Due to the permutation constraint, a sequence of jobs Π specifies a complete solution to the problem. Let us denote Cij(Π) the completion time on machine iof job in order jin sequence Π. Then, the maximum completion time or makespan of the solution Π can be computed using the following recursive expression: Cij(Π) = max{Ci−1,j;Ci,j−1}+pij ∀i= 1, . . . , m, j = 1, . . . , n (1) where pij denotes the processing time of job in position j(j= 1, . . . , n) on machine i(i= 1, . . . , m). Clearly, C0,j = 0 and Ci,0= 0. Then, Cmax =Cmn. Among all possible sequences, the goal is to find the one yielding the minimum makespan. This decision problem is well-known to be NP-hard for m > 2. In our research we assume that the processing times are random variables with expected value ˜pij. The objective is here to minimise the expected makespan. Clearly, since pij are random variables, so are Cij, see (1). An estimate of the values of Cij – denoted as ˜ Cij – can be computed using the expected value of the processing times, i.e.: ˜ Cij(Π) = max{˜ Ci−1,j;˜ Ci,j−1}+ ˜pij ∀i= 1, . . . , m, j = 1, . . . , n (2) also ˜ C0,j = 0 and ˜ Ci,0= 0. The stochastic behaviour of the flowshop motivates that the completion times of the jobs in the initial schedule (see Figure 1a) do not have to be the same as the actual completion times when the schedule is executed (see Figure 1b). More specifically, whenever job in position jin sequence Π has completed its processing on the first machine of the flowshop, this machine is available for the next job. In this situation, two options are possible: •To proceed with the next job in Π, that is, to enter job in position j+ 1 in the first machine. We will refer to this option as to no rescheduling, as it results in sequencing the jobs according to the initial sequence Π (except perhaps some right/left shifting of the jobs). This situation is depicted in Figure 1c. 8
(a) Initial schedule (b) Actual completion time of the job in the first machine and new (expected) machine availability (c) No rescheduling (except left shifting of the scheduled jobs) (d) Rescheduling in view of the expected machine availability Figure 1: Options when the actual processing times on the first machine do not match the expected processing times. 9
When doing both choices we can take into account the results by Perez-Gonzalez and Framinan (2009), which indicate that the procedures for the Fm||Cmax problem also perform well for the availability-constrained version unless aiare extremely different (i.e. several times the magnitude of the processing times of the jobs). Clearly, this is not our case as the increases of these unavailability periods should not exceed, on average, the mean processing times of the jobs. Therefore, we can adapt the IG algorithm to the problem under consideration, with the same parameters as in the generation of the initial sequence, and be quite confident on obtaining high-quality results for the problem with machine availability constraints. For the second option, we adapt the NEH heuristic (Nawaz et al., 1983), which is known to be the most efficient constructive heuristic for the unconstrained problem. In this manner, we can model the two options described above. 3. The first job of the new sequence obtained by some of the methods described in the above step enters in the first machine of the flowshop. 4.3 Rescheduling policies The rescheduling procedure described in the previous section can be triggered every time a job is completed in the first machine of the shop, or upon the fulfilment of additional requirements. Perhaps the simplest way –and certainly the most popular in the literature reviewed in Section 2– is to perform a continuous rescheduling (CR) policy, i.e. to trigger the rescheduling procedure every time that a job finishes its processing in the first machine of the shop. However, on the one hand continuous rescheduling is very time consuming, as it has been already discussed. On the other hand, such frequent rescheduling may introduce some instability in the system so its performance may deteriorate. Therefore, we also propose two Event-Driven Rescheduling policies that are described in the next subsections. 4.3.1 Discrepancy-Based Policy Clearly, if the variability of the processing times is minimal, then there would be no need to reschedule, as the actual completion times would be very similar to those expected from the base schedule. 16
In this regard, it seems intuitive to argue that the need for rescheduling increases as the discrepancy between the expected completion times and the actual processing times becomes higher. Therefore, our first proposal is a policy labelled Discrepancy-Based Rescheduling or DBR, which, for each job jwhich has just finished its processing on the first machine, it measures the relative discrepancy between the expected completion time of this job in the first machine and its actual completion time on this machine. If this relative discrepancy exceeds a certain value δ(a parameter of the policy), then the rescheduling procedure is triggered. More specifically, the procedure is triggered if the following condition holds: ˜ C1,j −C1,j ˜ C1,j > δ (6) It is clear that δgreatly influences the behaviour of this policy: for small δvalues, this policy is expected to be similar to a CR policy, whereas for large δvalues, it is expected to be similar to not to reschedule. 4.3.2 Critical Path Rescheduling Policy The second rescheduling policy proposed in this paper is based on the concept of critical path of a flowshop (Nowicki and Smutnicki, 1996). Given a sequence Π = (π1, . . . , πn), a graph G(Π) = (N, E) can be obtained by connecting N=n·mnodes (representing each operation of the njobs on the mmachines of the flowshop), each one of weight ˜pπi,j. A set of arcs Econnects each node (i, j) with nodes (i+ 1, j) and (i, j + 1). The resulting graph is depicted in Figure 4a. In this graph, the critical path is the longest path to go from node (1,1) to node (n, m). Clearly, the length of the critical path is the (deterministic) makespan of the sequence Π, i.e.: ˜ Cmax(Π) = X ∀(i,j)∈CP (Π) ˜pi,j where CP (Π) is the set of nodes in the critical path of sequence Π. The interpretation of the critical path in the Gantt chart is given in Figure 4b. In a scenario with variable processing times it is clear that, if the realization of the processing times of a given operation changes the previous critical path, then the makespan of this sequence 17
(a) Graph representation and critical path (b) Gantt chart with critical path Figure 4: Example of the critical path concept. might be greatly altered with respect to that initially expected. In contrast, if the actual processing times of the current sequence do not change the initial critical path, then possibly there is no need to reschedule the remaining jobs, as possibly some left/right shifting will suffice. Therefore, our proposal is to use this alteration in the critical path as a mechanism to trigger the rescheduling. More specifically, after the completion time of job jin the first machine, we check whether the actual completion times have modified the critical path with respect to that of the current sequence. If the resulting critical path is not the same, then the rescheduling procedure is triggered. This policy is labelled CPR (Critical Path Rescheduling) policy, and does not require any parameter. 5 Computational experience In this section we describe the experiments carried out to respond to the research questions posed in Section 1. In Section 5.1 we discuss the design of the experiments, while in Section 5.2 we present the results of the computational experience. 5.1 Design of the Experiments The different procedures described in Section 4 are applied to the testbed of Taillard (1993), that contains 120 flowshop scheduling instances with different numbers of jobs and machines. This testbed has become an standard for the evaluation of the effectiveness of flowshop scheduling techniques, and it is known to contain instances for which it is difficult to find their optimal values, as the 18
processing times in the instances have been chosen so that a lengthy tabu search procedure yields solutions which are relatively far from their lower bounds. Out of these 120 instances, the first 100 ones have been selected for our experimentation. Aside from the enormous computation times required for the simulation of the re-sequencing procedure in the biggest instances (see below), we have opted for this subset of instances in order to ensure that the IG procedure is able to find very good solutions within the allocated CPU time. Therefore, the following combinations have been tested: (n, m)∈ {(20,5),(20,10),(20,20),(50,5),(50,10),(50,20),(100,5),(100,10),(100,20),(200,10)}, with 10 instances of each problem size. Note that other testbeds for permutation flowshop problems exist, such as the VRF testbed by Vallada et al. (2015). However, this testbed is relatively new and it seems reasonable to think that the best-known values of these instances are not so close to their optima as those in Taillard’s testbed, which, in many cases, are known to be in fact optimal. Since we will use these deterministic best-known values to compute the quality of the approaches (see Section 5.2), we believe that using these, in principle, tighter upper bounds would produce more consistent results. The processing times in the instances are assumed to follow a log normal distribution, which has two parameters: mean µand standard deviation σ. This distribution has been widely employed to model stochastic processing times (see e.g. Baker and Trietsch, 2011, Baker and Altheimer, 2012, or Framinan and Perez-Gonzalez, 2015). Furthermore, we can easily control the variability of the processing times by setting different levels of coefficient of variation cv =σ µ. More specifically, we set cv ∈ {0.5,1,1.5}, which are assumed to represent a low, medium and large variability respectively in manufacturing shop floors (see Hopp and Spearman, 2008). In this manner, the processing times given in Taillard’s testbed are interpreted as the mean value of these processing times (µ= ˜pij) and σij the corresponding standard deviation is obtained once cv is given, i.e. σij = ˜pij ·cv. For each instance in the testbed, different rescheduling strategies have been tested. These are labelled using the format (B, {RP, RA}), where Bindicates how the base schedule is obtained, RP indicates the rescheduling policy –i.e. when the rescheduling algorithm is triggered–, and RA indicates the rescheduling algorithm employed. Using this notation, the following options have been tested: •(IG, −): The IG procedure described in Section 4.2 has been used to develop an initial 19
schedule, which has not been subsequently modified. •(IG, {CR, IG}): The IG procedure has been used to develop an initial schedule, and the CR rescheduling procedure described in Section 4.3 using the IG algorithm is triggered every time a job has finished its processing in the first machine. •(Rand, {CR, IG}): A random sequence has been used as initial schedule, and the CR rescheduling procedure using the IG algorithm is triggered every time a job has finished its processing in the first machine. •(IG, {CR, NEH}): The IG procedure has been used to develop an initial schedule, and the CR rescheduling procedure using the NEH heuristic is triggered every time a job has finished its processing in the first machine. •(IG, {DBR(δ), IG}): The IG procedure has been used to develop an initial schedule, and the DBR rescheduling procedure described in Section 4.3.1 using the IG algorithm is triggered if the conditions in Equation (6) have been fulfilled when a job has finished its processing in the first machine, i.e. every time that the discrepancy has been greater than δ∈ {0.25,0.5}. For δ > 0.5, preliminary experiments have detected that the rescheduling procedure was triggered for all jobs, therefore it was equivalent to a CR policy. •(IG, {CP R, IG}): The IG procedure has been used to develop an initial schedule, and the CPR rescheduling procedure described in Section 4.3.2 using the IG algorithm is triggered if the new information implies a change on the critical path of the current schedule. The computational effort carried out involves solving 30 replications of 100 problem sizes for each of the 7 options described above. Three out of these 7 options involve invoking of the IG algorithm n−1 times with a time limit of 30 seconds for each coefficient of variation, which makes a total equivalent computation time of 22.18 days only for the three continuous rescheduling options. In total, the experimentation has taken the equivalent of several months of computations. 20
n m (IG, −) (IG, {CR, IG}) (Rand, {CR, IG}) (IG, {CR, NEH}) (IG, {DBR(0,25), IG}) (IG, {DBR(0,5), IG}) (IG, {CP R, IG}) 20 5 21.379 19.671 23.263 20.475 20.880 22.651 19.368 20 10 27.296 26.669 30.791 26.396 26.153 26.467 25.899 20 20 25.144 25.130 27.250 26.399 26.033 24.973 24.489 50 5 17.066 15.218 16.477 15.496 15.195 15.527 13.794 50 10 25.566 24.433 27.024 26.382 24.550 24.117 23.810 50 20 29.551 28.315 29.804 31.387 27.792 28.042 28.069 100 5 13.352 12.084 12.668 12.234 12.210 12.146 11.893 100 10 20.307 18.468 20.449 19.900 18.546 18.088 17.381 100 20 26.907 25.531 27.027 28.026 25.449 24.175 23.915 200 10 16.209 14.892 15.246 15.596 14.862 14.319 13.101 Average 22.952 21.724 23.862 22.966 21.868 21.798 20.958 Table 1: Average RPD for cv = 0.5 n m (IG, −) (IG, {CR, IG}) (Rand, {CR, IG}) (IG, {CR, NEH}) (IG, {DBR(0,25), IG}) (IG, {DBR(0,5), IG}) (IG, {CP R, IG}) 20 5 43.532 41.847 44.694 44.723 41.579 41.216 41.178 20 10 56.218 54.068 61.854 56.257 56.230 57.741 55.778 20 20 58.581 58.697 61.698 57.995 58.031 59.487 57.994 50 5 34.430 33.818 34.346 33.160 33.549 33.088 32.623 50 10 52.806 52.346 52.290 53.082 51.766 52.501 52.105 50 20 62.462 60.403 64.844 65.048 62.077 62.144 61.432 100 5 26.828 25.543 26.266 26.733 26.311 27.708 25.211 100 10 41.359 39.779 42.045 41.171 41.239 40.747 38.105 100 20 57.289 56.668 56.783 58.786 56.088 54.396 54.649 200 10 33.607 31.766 32.636 31.631 32.613 31.571 30.053 Average 48.167 47.019 49.424 48.551 47.430 47.670 46.564 Table 2: Average RPD for cv = 1.0 n m (IG, −) (IG, {CR, IG}) (Rand, {CR, IG}) (IG, {CR, NEH}) (IG, {DBR(0,25), IG}) (IG, {DBR(0,5), IG}) (IG, {CP R, IG}) 20 5 65.460 65.073 65.835 62.049 58.928 67.254 59.371 20 10 77.959 77.775 82.043 83.921 83.919 78.731 81.644 20 20 86.766 87.920 93.570 87.619 91.258 90.188 87.475 50 5 47.192 46.228 45.964 49.411 47.741 49.529 45.885 50 10 80.147 76.678 81.362 74.654 76.875 75.806 76.062 50 20 94.308 95.021 99.883 98.629 100.453 95.496 95.954 100 5 40.061 38.407 40.332 40.101 40.019 41.588 38.461 100 10 60.820 60.981 62.597 62.077 61.562 62.493 60.013 100 20 88.549 86.243 85.850 87.753 85.264 85.600 84.904 200 10 49.350 48.524 48.445 49.541 48.973 50.122 45.705 Average 71.251 70.481 73.048 71.802 71.780 71.854 69.974 Table 3: Average RPD for cv = 1.5 21
5.2 Results The results for each value of cv are summarised in Tables 1, 2 and 3 in terms of the Average Relative Percentage Deviation (RPD), where the RPD of instance ifor a procedure pis computed as: RP D(i, p) = Cmax(i, p)−C∗ max(i) C∗ max(i)·100 (7) where Cmax(i, p) is the makespan obtained by applying procedure pon instance i, and C∗ max is the best-known value for instance iassuming deterministic processing times. In order to compute the savings in triggering the rescheduling procedures achieved by the different event-driven rescheduling policies –i.e. (IG, {DBR(0,25), IG}), (IG, {DBR(0,5), IG}) and (IG, {CP R, IG})–, we also measure the relative reduction in the number of times (RRN) that the rescheduling processes is triggered for a given rescheduling policy with respect to that of the continuous rescheduling. More specifically, for each instance iand a rescheduling policy pwe compute: RRN(i, p) = NCRi−NRi,p NCRi (8) where NCRiis the number of times that a continuous rescheduling policy would trigger the rescheduling process (i.e. the number of jobs in instance iminus one), and NR(i, p) is the number of times that rescheduling policy ptriggers the rescheduling process. The average RNN values for each problem size are shown in Table 4. In order to check the statistical significance of the results, the 95% confidence intervals for the different coefficient of variations are shown in Figures 5, 6, and 7 respectively. Finally, the results of Tukey HSD are shown in Tables 5, 6, and 7. An ANOVA conducted on all the results establishes that the most significant factor is the coefficient of variation, therefore it makes sense to divide the discussion of the results along the different values of cv. For scenarios with low variability (i.e. cv = 0.5), it can be seen that there are advantages on rescheduling as compared with no rescheduling as long as the base schedule is a good one and we use an excellent rescheduling algorithm (in our case, IG). This can be clearly seen in Table 1 and in Figure 5 by checking that there are statistically significant differences be- 22
Problem size cv = 0.5cv = 1.0cv = 1.5 n m δ = 0.25 δ= 0.5CPR δ = 0.25 δ= 0.5CP R δ = 0.25 δ= 0.5CPR 20 5 0.487 0.937 0.905 0.379 0.898 0.814 0.376 0.860 0.737 20 10 0.560 0.993 0.761 0.463 0.958 0.657 0.394 0.908 0.595 20 20 0.895 1.000 0.794 0.745 0.993 0.696 0.670 0.975 0.599 50 5 0.429 0.901 0.948 0.305 0.844 0.882 0.254 0.752 0.826 50 10 0.274 0.803 0.908 0.123 0.701 0.854 0.101 0.604 0.821 50 20 0.384 0.987 0.847 0.205 0.965 0.801 0.117 0.883 0.772 100 5 0.417 0.823 0.969 0.283 0.773 0.939 0.220 0.704 0.909 100 10 0.280 0.757 0.953 0.086 0.679 0.918 0.057 0.571 0.895 100 20 0.296 0.804 0.926 0.084 0.752 0.899 0.028 0.649 0.876 200 10 0.283 0.676 0.982 0.119 0.623 0.957 0.046 0.525 0.947 Average 0.447 0.889 0.890 0.297 0.840 0.829 0.246 0.767 0.781 Table 4: Average RRN for the event-driven policies and the different coefficients of variations. tween (IG, −) and any of the rescheduling policies that use IG for both schedule generation and rescheduling. (IG, −) obtains sequences that are, on average, around 10% worse than those obtained by the (IG, {CP R, IG}) policy (the best-performing rescheduling policy) and 3.6% worse than those obtained by the (IG, {CR, IG}) policy (the worst-performing rescheduling policy). If these differences are measured using the best of the tested policies as C∗ max(i), this figure is about 27% for (IG, {CP R, IG}) and about 10% for (IG, {CR, IG}). This speaks for substantial performance differences between these cases. The results also show that these potential rescheduling advantages blur if the base schedule is not excellent (see (Rand, {CR, IG}) in Figure 5) or if the rescheduling algorithm is not excellent, see (IG, {CR, NEH}). Among the rescheduling policies that can be implemented, the results also show that it is better to implement event-driven rescheduling policies as compared to continuous rescheduling. Particularly, the proposed Critical-Path Rescheduling policy outperforms the rest of the policies, and this difference is statistically significant, as it can be seen in the Tukey HSD data in Table 5. Furthermore, it can be seen in Table 4 that the CPR policy requires a very small number of reschedules (a saving of around 90% with respect to CR) and does not need setting any parameter, which represents another advantage as compared to DBR policies. When analysing the trade-off between a good base schedule followed by no rescheduling, and a bad base schedule followed by a good rescheduling algorithm (i.e. (IG, −) vs. (Rand, {CR, IG}) in Figure 5), the second option is better, not only on average but also in statistical terms. This 23
Figure 5: Mean and 95% CI for cv = 0.5 fact speaks for the relative robustness of deterministic scheduling in front of low variability (i.e. cv = 0.5) of the processing times. For an scenario with medium variability (cv = 1.0), Figure 6 shows that there are advantages on rescheduling as compared with no rescheduling as long as the base schedule is a good one and we use a combination of an excellent rescheduling algorithm (in our case, IG) and a suitable rescheduling policy (Critical Path). Otherwise, there may be advantages in rescheduling with respect to the average values (see Table 2), but they are not statistically significant. The difference between (IG, {CP R, IG}) and (IG, −) for this case are around 5% with respect to deterministic scheduling, and around 8% with respect to the best tested option. Therefore, although the differences between the strategies shrink, there are still substantial differences between them. 24
Figure 6: Mean and 95% CI for cv = 1.0 Among the rescheduling policies, (IG, {CPR, IG}) is still the best one regarding the average values, and also taking into account the smaller number of times that the rescheduling procedure is triggered, see Table 4. Finally, when analysing the trade-off between a good base schedule followed by no rescheduling, and a bad base schedule followed combined with a good rescheduling algorithm (i.e. (IG, −) vs. (Rand, {CR, IG})in Figure 6), the second option is still better with respect to the average quality of the solutions, although there are not statistically significant differences between them, see Table 6. Finally, for an scenario with high variability (cv = 1.5), there are no statistically significant differences between the different options of rescheduling and not rescheduling when all problem sizes are aggregated. However, the analysis of the larger instances (n= 200) reveals that there are statistical differences between the methods (see Figure 8). This is indicating that, even for these 25
Nawaz, M., Enscore Jr., E., and Ham, I. (1983). A heuristic algorithm for the m-machine, n-job flow-shop sequencing problem. Omega, 11(1):91–95. Nowicki, E. and Smutnicki, C. (1996). A fast tabu search algorithm for the permutation flow-shop problem. European Journal of Operational Research, 91(1):160–175. Ovacik, I. and Uzsoy, R. (1994). Exploiting shop floor status information to schedule complex job shops. Journal of Manufacturing Systems, 13(2):73–84. Perez-Gonzalez, P. and Framinan, J. (2009). Scheduling permutation flowshops with initial availability constraint: Analysis of solutions and constructive heuristics. Computers and Operations Research, 36(10):2866–2876. Pfeiffer, A., K´ad´ar, B., and Monostori, L. (2007). Stability-oriented evaluation of rescheduling strategies, by using simulation. Computers in Industry, 58(7):630–643. Rahman, H., Sarker, R., and Essam, D. (2013). Permutation flow shop scheduling with dynamic job order arrival. In 2013 IEEE Conference on Cybernetics and Intelligent Systems (CIS), pages 30–35. Rahmani, D. and Heydari, M. (2014). Robust and stable flow shop scheduling with unexpected arrivals of new jobs and uncertain processing times. Journal of Manufacturing Systems, 33(1):84– 92. Ruiz, R. and St¨utzle, T. (2007). A simple and effective iterated greedy algorithm for the permutation flowshop scheduling problem. European Journal of Operational Research, 177(3):2033–2049. Sabuncuoglu, I. and Kizilisik, O. B. (2003). Reactive scheduling in a dynamic and stochastic fms environment. International Journal of Production Research, 41(17):4211–4231. Swaminathan, R., Pfund, M., Fowler, J., Mason, S., and Keha, A. (2007). Impact of permutation enforcement when minimizing total weighted tardiness in dynamic flowshops with uncertain processing times. Computers and Operations Research, 34(10):3055–3068. Taillard, E. (1993). Benchmarks for basic scheduling problems. European Journal of Operational Research, 64(2):278–285. Vallada, E., Ruiz, R., and Framinan, J. (2015). New hard benchmark for flowshop scheduling problems minimising makespan. European Journal of Operational Research, 240:666–677. Vieira, G. E., Herrmann, J. W., and Lin, E. (2003). Rescheduling manufacturing systems: A framework of strategies, policies, and methods. Journal of Scheduling, 6(1):39–62. Waschneck, B., Altenm¨uller, T., Bauernhansl, T., and Kyek, A. (2017). Production scheduling in complex job shops from an industrie 4.0 perspective: A review and challenges in the semiconductor industry. In CEUR Workshop Proceedings. 32