New approximate algorithms for the customer order scheduling problem with total completion time objective∗ Jose M. Framinan1† , Paz Perez-Gonzalez1 1Industrial Management, School of Engineering, University of Seville, Ave. Descubrimientos s/n, E41092 Seville, Spain, {framinan,pazperez}@us.es September 18, 2016 Abstract In this paper, we study a customer order scheduling problem where a number of orders, composed of several product types, have to be scheduled on a set of parallel machines, each one capable to process a single product type. The objective is to minimise the sum of the completion times of the orders, which is related to the lead time perceived by the customer, and also to the minimisation of the work-in-process. This problem has been previously studied in the literature, and it is known to be NP-hard even for two product types. As a consequence, the interest lies on devising approximate procedures to obtain fast, good performing schedules. Among the different heuristics proposed for the problem, the ECT (Earliest Completion Time) heuristic by Leung et al. (2005b) has turned to be the most efficient constructive heuristic, yielding excellent results in a wide variety of settings. These authors also propose a tabu search procedure that constitutes the state-of-the-art metaheuristic for the problem. We propose a new constructive heuristic based on a look-ahead mechanism. The computational experience conducted shows that it clearly outperforms ECT, while having both heuristics the same computational complexity. Furthermore, we propose a greedy search algorithm using a specific neighbourhood that outperforms the existing tabu search procedure for different stopping criteria, both in terms of quality of solutions and of required CPU effort. Keywords: Order Scheduling, Completion Times, Heuristics ∗Preprint submitted to Computers & Operations Research. DOI: http://dx.doi.org/10.1016/j.cor.2016.09.010 †Corresponding author. Tel.: +34-954487214. 1
1 Introduction In classic scheduling literature, jobs to be processed are treated as individual entities possibly belonging to different customers, and hence the objectives sought are related to the completion times of the individual jobs, or to the differences between the completion times and their due dates or deadlines. However, in many real-life situations, a customer order is composed of different products that have to be processed in the shop, and therefore it may be sensible to pursue objectives related to the completion of the order as a whole rather than to the individual jobs in the order. This is caused by the fact that many customers require to receive the complete order and therefore, from their viewpoint, only the completion time of the full order is relevant (Ahmadi et al., 2005). Additional reasons for this assumption include the fact that shipping partial orders results in additional cost of transport, aside than causing a proliferation of documentation and extra management time (Blocher and Chhajed, 1996). Furthermore, if a final assembly of the jobs that compose the order has to be carried out, there is no interest in having just a fraction of these components, which indeed represents an extra-cost for the customer due to the corresponding inventory holding costs. In view of the frequency of real-life settings where this situation arises, a branch of scheduling labelled customer order scheduling has emerged as a new research area in order to respond to the ever increasing importance of customer satisfaction and short delivery times (Ahmadi et al., 2005), and the pre eminence of Make-To-Order production environments where it happens (Leung et al., 2005b). In this paper, we consider a case of customer order scheduling in which we have a facility with several machines in parallel. Each machine can produce one (and only one) particular product type, i.e. they are considered to be dedicated machines. On this productive environment, customer orders composed of some/all the product types that can be manufactured have to be scheduled. This problem was first formulated by Ahmadi and Bagchi (1990), and several practical applications of this model have been described, including finishing operations in the paper industry (Leung et al., 2005b), manufacturing of semi finished lenses (Ahmadi et al., 2005), the pharmaceutical industry (Leung et al., 2005a), or the assembly of operations (Leung et al., 2005b). Other specific applications can be seen in Blocher and Chhajed (1996), Yang and Posner (2005), and Yang (2005). Among the different objectives that can be set for the scheduling problem, perhaps the most 2
treated is the minimization of the sum of the completion times of the orders, which is related to the delivery times perceived by the customer. Note that minimising the sum (or average) of completion times of the order not only enables a time-based competition, but also aims at lowering the average work in process according to Little’s law. The resulting problem is usually denoted in the literature as P D|| PCj(see Leung et al., 2005b), and its NP-hardness was first established by Wagneur and Sriskandarajah (1993), although their proof contained a flaw (see Leung et al., 2005b), so its complexity remained uncertain until the problem was shown to be NP-hard in the strong sense even for two machines by Roemer and Ahmadi (1997). Other objectives also considered in the literature are the total tardiness (Lee, 2013), or weighted sum of completion time (Leung et al., 2007b; Wang and Cheng, 2007). Given the NP-hard nature of the problem, it is understandable that the focus of the researchers has been mainly on devising approximate procedures or heuristics to obtain good solutions for the problem in a reasonable CPU time, even if there is no optimality guarantee for these procedures. More specifically, several heuristics for the problem have been proposed by Sung and Yoon (1998); Ahmadi et al. (2005); Leung et al. (2005b), and Wang and Cheng (2007). Among then, the socalled ECT (Earliest Completion Time) heuristic by Leung et al. (2005b), also described in Ahmadi et al. (2005), has been shown to clearly outperforms the rest. Indeed, the performance of the ECT heuristic is exceptional according to the results obtained by Leung et al. (2005b). These authors use the ECT procedure as a starting solution of a tabu search procedure specifically designed for the problem, which is denoted in the following as TS(ECT). Therefore, both ECT and TS(ECT) constitute the best constructive and improvement heuristics for the problem, respectively. Furthermore, the effectiveness of the ECT heuristic is such that its adaptation (WECT - Weighted ECT) is also among the best heuristics for the related problem of minimising the weighted sum of the completion times (see Leung et al., 2007a; 2008). The ECT is a constructive heuristic that starts from an empty (partial) sequence and generates a sequence of orders one at a time, each time selecting as the next order to be appended at the end of the partial sequence the one that would be completed the earliest. Such exceptional performance of a pure greedy constructive heuristic suggests a peculiar structure of the solution space, and opens some opportunities for improvement by incorporating look-ahead elements that a greedy behaviour 3
may overlook. Along this idea, in this paper we propose a new constructive heuristic for the problem that exploits some special features of the problem. More specifically, when selecting a new order to be scheduled, our proposed heuristic balances the contribution of the order to the sum of the completion times with the estimated contribution of the non-scheduled orders. By using such tradeoff and providing a fast and relatively accurate estimation of the contribution of the non-scheduled orders, the proposed heuristic is shown to outperform ECT by a wide margin, being both heuristics of the same complexity. In addition, we design two specific local search mechanisms for the problem, and embed them into a Greedy Search Algorithm (GSA). The subsequent computational experience carried out shows that GSA outperforms the tabu search algorithm by Leung et al. (2005b) for different stopping criteria. The rest of the paper is organised as follows: In Section 2 we formalise the problem under consideration, and discuss its state-of-art. Section 3 is devoted to presenting the proposed heuristic (Section 3.1 ) and the GSA (Section 3.2), while an exhaustive computational experience is carried out in Section 4. Finally, Section 5 is devoted to discuss the main conclusions of the research. 2 Background The scheduling problem described in Section 1 can be formally stated as follows: There is a facility with mmachines in parallel. Each machine can produce one particular product type. There are ncustomer orders composed of some/all the product types that can be manufactured on the m machines. The total amount of processing required by order ion machine jis pij, i.e. order i contains a number of units of the product type manufactured in machine j, so it requires pij time units of this machine. Note that this is equivalent to say that the number of units of a product type requested is different for each customer, which reflects the usual real-life situation. A schedule or solution Π := (π1, π2, . . . , πn) is given by a permutation of ncomponents as it indicates the sequence in which the orders are processed. Let Cπi,j(Π) be the completion time of product type jin the order scheduled in the iposition in sequence Π. In this setting, it is clear that Cπi,j(Π) is given by the following recursive equation: 4
Cπi,j(Π) = Cπi−1,j(Π) + pπi,j i= 1, . . . , n, j = 1, . . . , m (1) where Cπ0,j(Π) := 0 ∀j.Cπi(Π) the completion time of order scheduled in position i-th is then: Cπi(Π) = max j=1,...,m{Cπi,j(Π)}(2) Similarly, C(Π) is the sum of the completion times of the orders scheduled according to Π. Obviously, C(Π) = Pn i=1 Cπi(Π). From the above definitions, it can be seen that a sequence can be evaluated anew in O(nm), being O(m) the computational cost of evaluating Cπi(Π) if all Cπi−1,j(Π) have been already computed. As mentioned in Section 1, several constructive heuristics have been proposed for the problem: •Shortest Total Processing Time (STPT) heuristic (Sung and Yoon, 1998). This heuristic –originally proposed for the weighted total completion time case– constructs a sequence of orders by starting with an empty schedule and selecting as the next order to be scheduled the one with the smallest total amount of processing over all mmachines among the non scheduled jobs. Clearly, the complexity of this heuristic is O(mn +nlog n), as pointed out in Leung et al. (2005b). •Shortest Maximum Processing Time (SMPT) heuristic (Sung and Yoon, 1998). This heuristic selects the order with the smallest maximum amount of processing time on any of the m machines. Its complexity is also O(mn+nlog n), and it was initially proposed for the weighted completion time case. •Smallest Maximum Completion Time (SMCT) heuristic (Wang and Cheng, 2007). This heuristic, also applicable for the weighted completion time case, first sequences the orders in non decreasing order of the processing times on each machine j. Consequently, msolutions are obtained, each one denoted as Πj:= (πj 1, . . . , πj n), j= 1, . . . , m. For each order k, an indicator Ik:= max1≤j≤m{Cπj r,j(Πj) : πj r=k}is computed. Then, a final solution Sis obtained by sorting the orders in non decreasing order of Ik. The complexity of this heuristic is determined by the iteration loop, as the initial sorting order is O(mn log n) whereas that 5
of the loop is O(n2m). •Earliest Completion Time (ECT) heuristic (Ahmadi et al., 2005; Leung et al., 2005b). This heuristic generates a sequence of orders one at a time; each time it selects as the next order the one that would be completed the earliest. Note that this heuristic can be implemented in a natural way in O(n2m) (Leung et al., 2005b), since it has niterations and, for each iteration, O(n) candidates have to be evaluated according to equation (2), which can be computed in O(m) since the completion times of the already scheduled jobs can be stored and the candidates do not need to be computed from scratch. In order to evaluate the effectiveness of the aforementioned heuristic, an extensive computational evaluation is carried out by Leung et al. (2005b), where all four heuristics above are compared. In their experimentation, it turns out that ECT is the most efficient heuristic in terms of the quality of the solutions, clearly outperforming the rest of heuristics. Such good performance is remarkable taking into account that it is basically a greedy heuristic. This fact may be indicating a special structure of the solution space, and opens some opportunities for improvement by carefully designing heuristics taking into account such structure. In the next section, we will discuss our proposal, which is based on properly assessing not only the contribution to the completion time done by the candidate order but also the estimated contribution of the unscheduled orders. 3 New approximate algorithms for the problem In this section, we present new algorithms for the problem under consideration. The first algorithm, discussed in Section 3.1, is a constructive heuristic for the problem based in the ideas presented at the end of the previous section. The aim is to obtain a fast heuristic that can yield better results than the ECT heuristic with the same complexity, thus being able to provide solutions in negligible CPU time. The second algorithm, discussed in Section 3.2, adopts a greedy search strategy and it is aimed at improving the solutions provided by constructive heuristics using the computation time in an efficient manner, thus being able to outperform the Tabu Search algorithm devised for the problem 6
by Leung et al. (2005b). To do so, the algorithm uses specific local search mechanisms based on the ECT heuristic. Furthermore, these mechanisms can be eventually used as standalone heuristics. 3.1 A new constructive heuristic As mentioned earlier, our proposal is based on incorporating a look-ahead mechanism in order to be able to assess, not only the potential contribution of the candidate orders to the objective function, but also an estimation of the contribution to the objective function of the non scheduled orders. More specifically, the proposed heuristic constructs a solution Π := (π1, . . . , πn) from a set U, representing the set of unscheduled orders. Initially, no order has been scheduled and consequently, Ucontains all orders. Then the heuristic starts an iterative process of nsteps: in step k(k= 1, . . . , n), each order in Uis selected as candidate to be appended at the end of Π. To select the chosen order among the candidates, for each order ωl∈ U, a (partial) sequence Slis formed by appending ωlat the end of Π, i.e. Sl= (π1, . . . , πk−1, ωl). Also, Rla set of remaining orders is obtained by removing ωlfrom U, i.e. Rl:= U − {ωl}. Then, the following indicator ψlis computed as follows: ψl=C(Sl) + 1 n−k+ 1C∗(Sl,Rl) (3) where C∗(Sl,Rl) is an estimate of the contribution to the completion times of the remaining unscheduled orders if ωlis to be appended at the end of Π to form Sl. Leaving aside for the moment how an estimation of the unscheduled orders can be computed, note that ψlcan be seen as a proxy for the objective function if order ωlis selected to be appended at the end of Π. More specifically, ψlis composed of two terms: the first one is the real contribution to the objective function caused by the completion times of orders in the partial sequence Π plus that of ωlwhen scheduled in position k, and the second term is the estimated contribution to the objective function caused by the orders not yet scheduled. The second term is weighted depending on the current iteration of the algorithm, i.e. for the first iterations there are many remaining orders which can be sorted in different ways, therefore the estimation of their contribution to the total completion time is more diffuse and should be smaller than in the last iterations, where there are less remaining orders and the estimation of their contribution would be rather similar to that of the final completion time. 7
It is clear then that the order with the lowest value of ψwould have the smallest contribution to the total completion times, therefore, in our proposal, the order with the lowest value of ψis removed from Uand appended at the end of Π. The procedure is repeated until U=∅. Regarding the computation of C∗(Sl,Rl), note that the contribution of the orders in Rlto the completion times will depend on the specific manner in which these orders are scheduled, as different ways to schedule these orders would yield different completion times. One option would be to schedule the jobs in Rlafter Slin the best possible manner, i.e. with the minimum contribution to the total completion times. However, it is clear that this would imply solving the original problem. Since the objective is to obtain an estimate of a sort of average contribution, we will evaluate such contribution assuming that the orders in Rlare scheduled following an specific sequence. Note that, in principle, since the orders in set Udepend on the current iteration of the algorithm, such sequence would have to be obtained for each iteration. Since this would increase the computation times, our proposal is to establish such sequence before the algorithm performs the iterations, so it does not have to be calculated for each Rl. More specifically, we will provide Ω a given sequence of all orders before starting the iterative procedure, and, at each iteration, we will compute C∗(Sl,Rl) as if the orders in Rlare scheduled in the relative ordering given by Ω. After selecting one of the orders in Ω to be scheduled, the order is appended at the end of the partial sequence and removed from Ω, so in the next iteration the sequence of the remaining orders does not have to be re-computed. Naturally, one may think that using as Ω a sequence yielding a very low completion time would provide a close estimation of the contribution of these orders and therefore may be tempted to obtain Ω by using e.g. the ECT heuristic. However, it has to be noted that, at each iteration of the proposed heuristic, the selected order would be extracted from Ω, and then there is no guarantee that the remaining unscheduled orders would make a good estimation. Therefore, rather than focusing on providing a sequence yielding a low completion time, we must focus on a robust ordering that ensures a good estimation even if an order is extracted in each iteration. To do so, we turn our attention to the SPT (Shortest Processing Time) rule, which is known to be optimal for job scheduling in a single machine with total completion time objective. This ordering has the advantage that, when certain job is extracted of an SPT sequence, the remaining jobs still comply 8
Procedure SPT-B for j= 1 to mdo Compute the workload of each order in machine j, i.e. Wj:= (p1j, p2j, . . . , pnj); Obtain Πjthe sequence of orders sorted in ascending (non descending) order of Wj; end r:= argminjC(Πj); Selects Πras the incumbent sequence; end Figure 1: Pseudo-code of the SPT-B procedure the SPT rule, therefore providing a consistent estimation no matter which jobs remain in the partial sequence. Since SPT cannot be applied to our problem in an straightforward manner as there are orders (not jobs) processed on mmachines in parallel, we propose a relatively simple procedure, named SPT-B in the following, inspired in the SPT: we consider each machine jand sort the processing times of each order on this machine according to the SPT rule. By doing so, we obtain mdifferent sequences, each one representing the application of the SPT in each of the machines of the facility. Among these msequences, we select the one yielding the lowest completion time. The pseudo code of the SPT-B procedure is presented in Figure 1. Using the above elements, the design and rationale of the heuristic have been discussed: an initial sequence Ω is obtained by sorting the orders according to SPT-B. Then, a solution Π is constructed by iteratively selecting one order in Ω that is removed from Ω and appended as the current last order of Π. At each step, the unscheduled order yielding the lowest value of ψcomputed as described in equation (3) is selected to be appended. The detailed pseudo-code of the heuristic is presented in Figure 2. Assuming, as usual, that n>m, the complexity of the heuristic is determined by the main iteration loop and not by the SPT-B procedure, as the complexity of the latter is O(m(nlog n+nm)) whereas that of the loop is O(n2m). As it can be seen, the complexity of the heuristic proposed is the same than that of ECT. 3.2 Greedy Search Algorithm In view of the good results obtained by the ECT heuristic, specific local search mechanisms based on this heuristic can be defined for the problem. The first of these mechanisms is labelled SHIFT-k. Its 9
•The SPT-B sorting order proposed in Section 3. This heuristic is included to check if the behaviour of NEW is mainly due to that of the SPT-B and therefore, the iterative mechanism in NEW is not worth the computational effort. •The heuristic proposed in Section 3.1 using the solution given by ECT as sorting order for the jobs in U, denoted as NEW-ECT in the following. This heuristic is included to verify the suitability of the SPT-B procedure as initial ordering for NEW as compared to that of ECT. •The heuristic proposed in Section 3.1 using the solution given by STPT as sorting order for the jobs in U, denoted as NEW-STPT in the following. This heuristic is included to verify the suitability of the SPT-B procedure as initial ordering for NEW as compared to that of STPT. •The SHIFT-kheuristic presented in Section 3.2. •The SHIFT-k-OPT heuristic presented in Section 3.2. The quality of the solutions provided by these heuristics is measured in terms of the Relative Percentage Deviation (RPD) obtained by each heuristic. The RPD is defined for heuristic hin the instance ias follows: RP Dih =Cih −Ci∗ Ci∗·100 (4) where Cih is the completion time obtained by heuristic hon instance iand Ci∗is the best-so-far total completion time available for instance i. For instances in TEST-1-S and TEST-2-S, Ci∗is the optimal solution obtained by exhaustive enumeration whereas for instances in TEST-1-B and TEST-2-B, Ci∗is the best total completion time obtained in the computational experiments by all heuristics under comparison, including those obtained by the lengthy TS and GSA presented in Section 4.3. Note that, in this section, we do not measure the computation effort of the heuristics under comparison as it is negligible. Tables 1 and 2 show the Average RPD (ARPD) values obtained for each problem size together with the standard deviation of the RPD for the small and big testbeds respectively. In view of these tables, the following comments can be done: 16
•As it can be seen in both tables, the heuristic proposed clearly outperforms the ECT heuristic, which was considered to be the best-so-far for the problem. •The quality of the proposal can be assessed not only in relative terms when compared with that obtained by other approximate procedures, but also with respect to the optimal solutions obtained for the small testbeds, being less than 0.8% on average for all testbeds. •Both for small and big testbeds, it can be seen that the superiority of the proposed heuristic does not depend on the problem size, or on the type of testbed, obtaining the best results for all cases. Additionally, the heuristic seems to be quite robust: it does not only has the lowest average standard deviation, but also its standard deviation is the lowest among the rest of the heuristics for all problem sizes in the two testbeds. This speaks for an exceptional performance as compared with the existing heuristics for the problem. This can be graphically seen in Figure 6, where 95% confidence intervals of the ARPD values for the two big testbeds are shown. In Figure 6 the worst-performing heuristic –SPT-B– has been excluded to make a more homogeneous scaling. •The sorting order SPT-B is, as expected, a rather bad heuristic itself, although this sorting order was not designed to be used in isolation. Indeed, SPT-B turns to be crucial for establishing the estimation mechanism for the proposed heuristic, which can be seen more clearly by comparing the results obtained by NEW with those found by NEW-ECT and NEW-STPT. From these results it can be seen that the strategy of focusing on the robust sorting ordering for the estimation is critical for the proposed algorithm. This fact can also be reinforced in an indirect manner by checking that STPT is able to outperform ECT as a starting solution. •The differences in the heuristics are statistically significant for the big testbeds, as shown in Table 3. The table show that, for both testbeds, the NEW heuristic constitutes a separate group, indicating statistically significant differences with the rest of the heuristics. A second group is formed by the SHIFT-k-OPT procedure, followed by SHIFT-k. All of them perform significantly better than ECT and that its experimental variant. 17
TEST-1-S ECT STPT NEW SPT-B NEW-ECT NEW-STPT SHIFT-kSHIFT-k-OPT m n Aver. St. Dev. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. 5 2 0.317 1.133 3.542 3.226 0.111 0.330 4.120 4.796 0.317 1.133 0.333 0.922 0.151 0.535 0.084 0.391 5 5 0.863 1.808 4.028 3.676 0.610 1.324 2.987 2.745 0.863 1.808 0.323 0.832 0.321 0.724 0.216 0.477 5 10 0.832 1.596 3.218 2.112 0.479 0.869 1.589 1.819 0.832 1.596 0.599 1.104 0.728 1.340 0.728 1.340 5 20 1.276 1.895 3.849 2.971 0.375 0.689 1.159 4.711 1.276 1.895 0.683 0.978 0.800 1.561 0.736 1.267 10 2 0.402 0.575 4.600 3.882 0.302 0.478 9.356 7.548 0.402 0.575 0.484 0.665 0.218 0.409 0.172 0.386 10 5 0.804 0.996 7.227 4.113 0.726 0.697 7.510 3.677 0.804 0.996 0.482 0.555 0.490 0.839 0.411 0.773 10 10 1.188 1.216 6.444 2.952 0.773 0.612 6.009 2.128 1.188 1.216 0.898 1.064 0.617 0.645 0.542 0.545 10 20 1.542 1.190 6.526 2.719 1.034 0.801 4.522 2.881 1.542 1.190 1.054 0.859 1.102 0.821 1.036 0.821 12 2 0.697 0.779 4.078 3.078 0.535 0.638 10.092 6.401 0.697 0.779 0.480 0.588 0.300 0.462 0.181 0.332 12 5 1.161 1.241 7.524 3.191 0.851 0.734 10.180 3.827 1.161 1.241 0.784 0.752 0.871 1.037 0.827 0.946 12 10 1.789 1.534 7.098 3.151 1.241 1.219 7.600 2.040 1.789 1.534 1.438 1.213 1.142 0.889 1.035 0.847 12 20 1.866 1.347 7.155 2.766 1.142 1.179 5.494 1.453 1.866 1.347 1.180 1.064 1.184 1.116 1.092 1.096 Avg. 1.061 1.276 5.441 3.153 0.682 0.798 5.885 3.669 1.061 1.276 0.728 0.883 0.660 0.865 0.588 0.769 TEST-2-S ECT STPT NEW SPT-B NEW-ECT NEW-STPT SHIFT-kSHIFT-k-OPT m n Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. 5 2 0.213 0.621 3.108 4.421 0.236 0.614 7.549 9.916 0.213 0.621 0.270 0.680 0.087 0.444 0.087 0.444 5 5 0.249 0.701 5.157 5.666 0.379 0.767 5.726 4.613 0.249 0.701 0.460 0.930 0.183 0.617 0.183 0.617 5 10 1.207 3.397 6.865 6.727 0.236 0.836 4.046 4.790 1.207 3.397 0.262 0.544 1.144 3.138 1.144 3.138 5 20 0.405 1.823 5.766 4.389 0.113 0.551 2.133 6.753 0.405 1.823 0.120 0.581 0.083 0.490 0.083 0.490 10 2 1.104 1.542 6.197 5.026 0.621 0.999 22.531 13.148 1.104 1.542 0.766 1.003 0.413 0.928 0.359 0.917 10 5 1.306 1.742 9.859 6.613 1.234 2.172 16.565 8.879 1.306 1.742 0.786 0.958 0.691 1.279 0.691 1.279 10 10 0.944 1.814 11.317 8.265 0.757 1.156 13.848 5.765 0.944 1.814 0.610 0.682 0.534 0.875 0.354 0.537 10 20 1.101 1.687 11.773 7.846 0.973 1.100 8.778 2.607 1.101 1.687 1.203 1.506 0.811 1.395 0.805 1.392 12 2 1.081 1.510 7.231 5.432 0.727 0.850 23.489 14.240 1.081 1.510 0.913 1.484 0.493 0.862 0.257 0.412 12 5 1.143 1.394 10.447 8.736 1.016 1.144 18.374 6.390 1.143 1.394 1.020 1.177 0.591 0.976 0.449 0.753 12 10 1.544 1.721 15.354 8.344 1.131 1.129 15.501 5.351 1.544 1.721 1.301 1.249 1.031 1.288 1.012 1.260 12 20 1.722 1.674 10.771 4.984 1.237 1.530 10.395 3.221 1.722 1.674 0.797 0.783 1.294 1.317 1.200 1.337 Avg. 1.002 1.636 8.654 6.371 0.722 1.071 12.411 7.139 1.002 1.636 0.709 0.965 0.613 1.134 0.552 1.048 Table 1: Average and Standard Deviation of RPD for the constructive heuristics on the small testbeds 18
TEST-1-B ECT STPT NEW SPT-B NEW-ECT NEW-STPT SHIFT-kSHIFT-k-OPT m n Aver. St. Dev. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. 2 20 1.193 0.746 4.712 2.723 0.545 0.350 15.060 7.615 1.193 0.746 0.909 0.503 0.654 0.398 0.466 0.367 2 50 1.637 0.684 3.724 2.118 0.429 0.178 18.925 5.832 1.637 0.684 1.420 0.485 0.891 0.395 0.691 0.333 2 100 2.519 0.643 3.353 2.017 0.395 0.127 24.545 4.700 2.519 0.643 2.051 0.374 1.395 0.382 1.087 0.280 2 200 2.946 0.418 2.749 1.084 0.340 0.105 25.873 3.077 2.946 0.418 2.388 0.212 1.680 0.250 1.339 0.171 5 20 1.295 0.823 6.342 2.386 0.959 0.697 11.966 3.530 1.295 0.823 1.068 0.893 0.853 0.586 0.743 0.539 5 50 1.943 0.602 6.907 2.117 1.060 0.436 16.675 2.683 1.943 0.602 1.493 0.397 1.457 0.384 1.379 0.369 5 100 1.761 0.326 6.545 1.906 1.034 0.225 16.718 2.181 1.761 0.326 1.610 0.367 1.350 0.248 1.284 0.242 5 200 1.965 0.284 4.974 1.520 1.111 0.191 17.887 1.777 1.965 0.284 1.829 0.350 1.594 0.234 1.513 0.220 10 20 1.793 0.896 8.511 2.561 1.241 0.743 9.912 1.960 1.793 0.896 1.293 0.797 1.424 0.778 1.368 0.767 10 50 1.925 0.673 8.762 2.332 1.422 0.585 13.076 1.653 1.925 0.673 1.544 0.480 1.642 0.529 1.548 0.485 10 100 1.731 0.433 7.420 1.967 1.292 0.367 13.879 1.393 1.731 0.433 1.526 0.284 1.574 0.406 1.537 0.400 10 200 1.693 0.273 5.550 1.368 1.084 0.190 14.023 1.152 1.693 0.273 1.428 0.229 1.593 0.230 1.576 0.225 20 20 1.866 0.934 7.800 2.769 1.082 0.678 7.985 1.533 1.866 0.934 1.768 1.021 1.577 0.794 1.491 0.758 20 50 1.799 0.664 8.646 2.249 1.382 0.659 10.577 1.210 1.799 0.664 1.550 0.556 1.566 0.462 1.513 0.416 20 100 1.628 0.330 8.141 2.072 1.312 0.329 11.468 0.961 1.628 0.330 1.477 0.438 1.522 0.299 1.481 0.293 20 200 1.598 0.218 6.196 1.390 1.146 0.228 11.388 0.859 1.598 0.218 1.338 0.237 1.545 0.207 1.533 0.204 Avg. 1.831 0.719 6.271 2.789 0.990 0.555 14.997 5.789 1.831 0.719 1.543 0.624 1.395 0.534 1.284 0.533 TEST-2-B ECT STPT NEW SPT-B NEW-ECT NEW-STPT SHIFT-kSHIFT-k-OPT m n Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. 2 20 1.595 1.120 7.245 3.705 1.065 0.893 32.654 14.073 1.595 1.120 1.407 0.961 0.570 0.512 0.348 0.407 2 50 2.437 0.943 7.222 3.758 0.757 0.302 41.252 9.695 2.437 0.943 2.187 0.818 1.142 0.488 0.829 0.393 2 100 2.989 0.916 6.151 3.209 0.706 0.295 47.241 12.398 2.989 0.916 2.347 0.615 1.404 0.508 1.051 0.416 2 200 3.859 0.760 3.919 2.286 0.552 0.190 53.304 7.700 3.859 0.760 2.820 0.346 1.795 0.433 1.346 0.283 5 20 2.025 1.359 12.810 5.814 1.620 0.935 29.334 8.900 2.025 1.359 1.409 0.828 1.401 1.224 1.166 0.917 5 50 3.472 1.101 12.846 4.238 1.833 0.649 33.836 6.901 3.472 1.101 2.602 0.683 2.617 0.897 2.373 0.759 5 100 3.862 0.804 11.004 3.360 2.107 0.639 39.776 4.907 3.862 0.804 3.155 0.807 3.010 0.711 2.882 0.692 5 200 4.570 0.863 10.314 3.396 2.437 0.626 40.022 3.623 4.570 0.863 3.942 0.806 3.599 0.577 3.393 0.544 10 20 2.432 1.790 14.899 4.974 1.820 1.153 23.119 6.404 2.432 1.790 1.910 1.311 1.905 1.319 1.788 1.249 10 50 3.008 1.314 16.168 5.470 2.121 1.062 31.109 4.777 3.008 1.314 2.611 0.788 2.536 1.114 2.454 1.058 10 100 3.339 0.964 14.096 3.536 2.277 0.689 34.445 2.634 3.339 0.964 2.778 0.548 2.908 0.834 2.842 0.785 10 200 3.428 0.580 11.914 2.692 2.307 0.370 35.602 2.787 3.428 0.580 3.012 0.550 3.118 0.516 3.029 0.526 20 20 2.695 1.772 13.318 4.291 1.697 1.486 18.737 4.317 2.695 1.772 2.063 1.173 2.106 1.358 1.915 1.262 20 50 2.804 0.920 15.891 4.236 2.278 1.107 26.465 3.641 2.804 0.920 2.534 0.780 2.432 0.895 2.334 0.883 20 100 2.717 0.554 14.654 3.784 2.156 0.670 30.790 3.692 2.717 0.554 2.354 0.611 2.475 0.483 2.419 0.479 20 200 2.935 0.527 12.485 2.943 2.067 0.340 32.691 2.284 2.935 0.527 2.411 0.567 2.728 0.490 2.701 0.508 Avg. 3.010 1.286 11.558 5.277 1.738 0.992 34.399 10.892 3.010 1.286 2.471 0.997 2.234 1.139 2.054 1.137 Table 2: Average and Standard Deviation of RPD for the constructive heuristics on the big testbeds 19
TEST-1-B Subset Constructive Heuristic Observations 1 2 3 4 5 NEW 480 0.990 SHIFT-K-OPT 480 1.284 SHIFT-k 480 1.395 NEW-STPT 480 1.543 ECT 480 1.831 NEW-ECT 480 1.831 Sig. 1.000 1.000 1.000 1.000 1.000 TEST-2-B Subset Constructive Heuristic Observations 1 2 3 4 5 NEW 480 1.738 SHIFT-K-OPT 480 2.054 SHIFT-k 480 2.234 NEW-STPT 480 2.471 ECT 480 3.010 NEW-ECT 480 3.010 Sig. 1.000 1.000 1.000 1.000 1.000 Table 3: HSD Tukey for the testbeds with big instances. Homogeneous subsets of ARPD values for the factor Constructive Heuristic Figure 6: 95% CI RPD for all constructive heuristics (except SPT-B) on the testbeds with big instances 20
4.3 Comparison of improvement heuristics In this section, we compare several improvement heuristics for the problem, including the GSA proposed in Section 3.2. More specifically, the following algorithms are compared: •The tabu search by Leung et al. (2005b) described in Section 2 as the best-so-far metaheuristic for the problem. This algorithm is denoted in the following TS(ECT), as it uses the ECT heuristic as starting solution. •The TS using NEW as initial solution. This algorithm is included in order to assess the beneficial effect of using NEW as initial solution as compared to using ECT. This algorithm is denoted in the following TS(NEW). •The GSA presented in Section 3.2. Different stopping criteria are tested for the algorithms, which are measured in terms of their ARPD and the CPU time effort. More specifically, for the two TS procedures, the number of iterations allowed without improvement is set to 10, 50, and 100. Similarly, the number of iterations allowed in GSA is 10, 50, and 100. Note however that the effort required in the iterations of GSA is different than that of TS, therefore the CPU time has to be computed as well. The results are shown in terms of RPD in Table 4, and in terms of CPU time in Table 6. According to these results, the following comments can be done: •Using the proposed heuristic (NEW) as a starting solution of the TS procedure by Leung et al. (2005b) improves the quality of solutions obtained by the tabu search regardless the stopping criteria. •The results obtained by the proposed GSA are better than those obtained by the TS(NEW) procedure and, consequently, than those obtained by the original TS for the three tested stopping criteria. On average, the best results obtained by the GSA procedure (GSA 100) are around 7 times lower than those obtained by the best TS procedure (TS(NEW) 100). The difference is more striking by taking into account that GSA 100 requires, on average, around 16 times less computational effort in the less favourable case. We think that these 21
Figure 7: 95% CI RPD for the improvement heuristics on the testbeds with big instances facts speak for the efficiency of the specific local search mechanism devised for the problem (SHIFT-k-OPT). •Tukey HSD for the three procedures under comparison are shown in Table 5. From these results, it can be seen that there are statistically significant differences among most procedures (see also Figure 7 where the 95% confidence intervals of ARPD are shown). As it can be seen, GSA stands out as the best procedure, being superior to all versions of TS, with the exception of GSA 10, which is not different than TS(NEW) 100. It has to be taken into account, however, that TS(NEW) 100 is, on average, around 100 times slower than GSA 10. •For the GSA proposed, the decrease in the ARPD as a function of the number of allowed iterations shows the scalability of the proposed procedure, particularly if compared with that of the TS. 5 Conclusions In this paper, we address the problem of scheduling orders composed of different product types in a parallel machine environment where each machine is able to manufacture a single product type. The objective is that of minimising the sum of the completion times of the orders. For this 22
TEST-1-B TS(ECT)10 TS(ECT)50 TS(ECT)100 TS(NEW)10 TS(NEW)50 TS(NEW)100 GSA10 GSA50 GSA100 m n Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. 2 20 0.086 0.216 0.085 0.216 0.060 0.128 0.038 0.093 0.038 0.093 0.038 0.093 0.053 0.068 0.013 0.032 0.004 0.014 2 50 0.059 0.081 0.055 0.082 0.052 0.082 0.008 0.016 0.004 0.006 0.002 0.005 0.070 0.033 0.036 0.025 0.029 0.022 2 100 0.043 0.053 0.040 0.052 0.040 0.052 0.005 0.006 0.003 0.005 0.002 0.005 0.063 0.018 0.042 0.014 0.038 0.014 2 200 0.039 0.042 0.039 0.042 0.039 0.042 0.003 0.006 0.003 0.006 0.002 0.006 0.031 0.015 0.023 0.009 0.021 0.008 5 20 0.169 0.259 0.117 0.179 0.094 0.153 0.141 0.243 0.098 0.230 0.078 0.231 0.132 0.114 0.050 0.066 0.030 0.055 5 50 0.178 0.164 0.119 0.127 0.106 0.123 0.096 0.119 0.070 0.113 0.061 0.109 0.227 0.102 0.113 0.080 0.069 0.055 5 100 0.155 0.114 0.120 0.116 0.108 0.102 0.113 0.098 0.080 0.085 0.061 0.062 0.127 0.072 0.039 0.044 0.031 0.045 5 200 0.097 0.077 0.088 0.078 0.085 0.080 0.059 0.038 0.053 0.041 0.045 0.040 0.104 0.049 0.025 0.025 0.011 0.018 10 20 0.240 0.328 0.174 0.303 0.127 0.265 0.212 0.323 0.101 0.158 0.073 0.107 0.229 0.191 0.074 0.077 0.055 0.072 10 50 0.477 0.259 0.392 0.213 0.355 0.209 0.263 0.215 0.196 0.203 0.145 0.189 0.278 0.142 0.072 0.091 0.040 0.067 10 100 0.374 0.245 0.312 0.246 0.263 0.183 0.295 0.158 0.249 0.156 0.236 0.164 0.132 0.065 0.031 0.037 0.007 0.019 10 200 0.341 0.141 0.307 0.150 0.291 0.148 0.307 0.084 0.280 0.091 0.261 0.089 0.202 0.068 0.026 0.027 0.000 0.000 20 20 0.310 0.306 0.232 0.280 0.191 0.249 0.280 0.308 0.198 0.282 0.113 0.186 0.209 0.166 0.060 0.085 0.041 0.077 20 50 0.427 0.325 0.322 0.307 0.258 0.279 0.490 0.408 0.446 0.404 0.382 0.394 0.302 0.168 0.083 0.084 0.032 0.064 20 100 0.668 0.335 0.628 0.338 0.575 0.343 0.627 0.217 0.592 0.234 0.571 0.249 0.219 0.143 0.039 0.054 0.000 0.000 20 200 0.856 0.225 0.786 0.238 0.754 0.238 0.708 0.176 0.695 0.182 0.684 0.180 0.343 0.101 0.043 0.049 0.000 0.000 Avg. 0.283 0.316 0.238 0.292 0.212 0.271 0.228 0.288 0.194 0.272 0.172 0.260 0.170 0.141 0.048 0.061 0.025 0.047 TEST-2-B TS(ECT)10 TS(ECT)50 TS(ECT)100 TS(NEW)10 TS(NEW)50 TS(NEW)100 GSA10 GSA50 GSA100 m n Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. Avg. Std. 2 20 0.032 0.114 0.032 0.114 0.022 0.103 0.030 0.113 0.030 0.113 0.030 0.113 0.063 0.122 0.029 0.065 0.012 0.029 2 50 0.051 0.095 0.049 0.096 0.047 0.096 0.008 0.016 0.008 0.016 0.008 0.016 0.098 0.053 0.044 0.030 0.030 0.023 2 100 0.049 0.062 0.049 0.062 0.048 0.062 0.003 0.006 0.002 0.006 0.002 0.006 0.085 0.030 0.044 0.024 0.039 0.021 2 200 0.035 0.040 0.035 0.040 0.035 0.040 0.001 0.002 0.001 0.002 0.001 0.002 0.040 0.011 0.033 0.011 0.029 0.012 5 20 0.299 0.309 0.234 0.288 0.219 0.271 0.281 0.405 0.214 0.383 0.212 0.385 0.246 0.304 0.041 0.091 0.023 0.081 5 50 0.265 0.259 0.235 0.250 0.214 0.259 0.159 0.135 0.137 0.141 0.126 0.143 0.289 0.115 0.093 0.081 0.051 0.068 5 100 0.246 0.169 0.223 0.168 0.213 0.169 0.194 0.255 0.178 0.252 0.159 0.256 0.140 0.077 0.026 0.041 0.018 0.040 5 200 0.261 0.159 0.254 0.160 0.251 0.163 0.144 0.091 0.134 0.091 0.129 0.090 0.071 0.048 0.010 0.018 0.001 0.004 10 20 0.588 0.713 0.492 0.712 0.473 0.715 0.499 0.722 0.241 0.440 0.168 0.403 0.222 0.260 0.026 0.079 0.016 0.043 10 50 0.625 0.490 0.519 0.492 0.477 0.491 0.434 0.327 0.325 0.244 0.218 0.221 0.423 0.224 0.123 0.111 0.058 0.088 10 100 0.650 0.359 0.591 0.354 0.544 0.369 0.482 0.250 0.440 0.235 0.419 0.248 0.217 0.096 0.042 0.060 0.013 0.038 10 200 0.612 0.209 0.585 0.216 0.574 0.208 0.512 0.145 0.469 0.137 0.461 0.132 0.153 0.095 0.023 0.028 0.000 0.000 20 20 0.542 0.771 0.228 0.284 0.193 0.262 0.326 0.382 0.205 0.290 0.195 0.292 0.265 0.340 0.036 0.073 0.027 0.053 20 50 0.652 0.435 0.530 0.399 0.489 0.388 0.562 0.357 0.393 0.291 0.353 0.302 0.470 0.202 0.079 0.100 0.017 0.050 20 100 0.746 0.371 0.693 0.386 0.645 0.353 0.665 0.423 0.604 0.341 0.569 0.351 0.234 0.149 0.028 0.056 0.000 0.003 20 200 0.962 0.256 0.939 0.264 0.930 0.261 0.901 0.268 0.850 0.239 0.839 0.236 0.241 0.101 0.052 0.057 0.000 0.000 Avg. 0.413 0.460 0.355 0.408 0.336 0.400 0.325 0.398 0.264 0.331 0.243 0.325 0.204 0.205 0.046 0.070 0.021 0.047 Table 4: Average and Standard Deviation of RPD for the improvement heuristics on the big testbeds 23
TEST-1-B Subset Improvement Heuristic Observations 1 2 3 4 5 GSA100 480 0.0255 GSA50 480 0.0481 GSA10 480 0.1700 TS(NEW) 100 480 0.1720 TS(NEW) 50 480 0.1941 0.1941 TS(ECT) 100 480 0.2123 0.2123 TS (NEW) 10 480 0.2278 TS(ECT) 50 480 0.2385 TS(ECT) 10 480 0.2825 Sig. 0.4497 0.3598 0.7358 0.2492 1.0000 TEST-2-B Subset Improvement Heuristic Observations 1 2 3 4 5 GSA100 480 0.0208 GSA50 480 0.0456 GSA10 480 0.2035 TS(NEW) 100 480 0.2429 0.2429 TS(NEW) 50 480 0.2643 TS (NEW) 10 480 0.3249 TS(ECT) 100 480 0.3360 TS(ECT) 50 480 0.3554 TS(ECT) 10 480 0.4135 Sig. 0.8478 0.2771 0.9272 0.6381 1.0000 Table 5: HSD Tukey for big instances testbeds. Homogeneous subsets of ARPD values for the factor Improvement Heuristic 24
TEST-1-B n m TS(ECT) 10 TS(ECT) 50 TS(ECT) 100 TS(NEW) 10 TS(NEW) 50 TS(NEW) 100 GSA 10 GSA 50 GSA 100 20 2 0.02 0.07 0.10 0.02 0.08 0.16 0.00 0.01 0.02 20 5 0.03 0.13 0.20 0.04 0.13 0.31 0.01 0.02 0.04 20 10 0.07 0.20 0.25 0.06 0.19 0.40 0.01 0.04 0.07 20 20 0.10 0.33 0.48 0.11 0.34 0.60 0.01 0.06 0.12 50 2 0.41 0.81 1.53 0.44 0.82 1.50 0.03 0.12 0.22 50 5 0.84 1.79 3.25 0.83 1.75 3.21 0.06 0.24 0.41 50 10 1.23 2.81 8.22 1.23 2.80 5.28 0.10 0.40 0.66 50 20 2.37 5.04 13.46 2.49 5.06 10.44 0.17 0.63 1.01 100 2 4.47 7.97 27.64 4.90 8.48 13.53 0.18 0.63 1.01 100 5 10.17 20.28 88.12 10.36 20.06 37.47 0.35 1.11 2.06 100 10 15.92 34.76 84.71 15.92 35.04 63.51 0.59 1.92 3.70 100 20 28.63 55.73 121.00 28.97 56.44 106.89 0.97 3.56 6.91 200 2 77.79 100.66 297.40 87.81 112.61 157.36 0.91 3.40 6.48 200 5 190.00 260.46 595.65 190.26 261.07 354.12 2.30 7.94 15.03 200 10 350.09 500.25 970.69 351.50 503.24 727.41 4.46 14.45 28.57 200 20 492.60 862.04 1618.16 506.35 886.34 1366.59 8.15 28.41 56.65 Avg. 73.42 115.83 239.43 75.08 118.40 178.05 1.14 3.93 7.68 TEST-2-B n m TS(ECT) 10 TS(ECT) 50 TS(ECT) 100 TS(NEW) 10 TS(NEW) 50 TS(NEW) 100 GSA 10 GSA 50 GSA 100 20 2 0.01 0.07 0.09 0.01 0.07 0.17 0.00 0.01 0.02 20 5 0.03 0.13 0.15 0.03 0.12 0.26 0.00 0.02 0.04 20 10 0.05 0.17 0.24 0.05 0.18 0.33 0.01 0.04 0.07 20 20 0.08 0.32 0.31 0.09 0.32 0.52 0.01 0.06 0.11 50 2 0.38 0.80 1.18 0.37 0.74 1.59 0.03 0.12 0.22 50 5 0.65 1.47 2.77 0.66 1.46 3.03 0.06 0.24 0.41 50 10 1.02 2.62 5.08 1.01 2.63 4.51 0.09 0.39 0.62 50 20 1.62 4.31 7.91 1.63 4.29 7.52 0.17 0.61 1.00 100 2 3.48 6.14 11.00 3.45 6.36 10.92 0.17 0.61 0.98 100 5 9.18 17.00 27.73 9.13 16.91 27.06 0.35 1.10 1.99 100 10 12.13 25.09 42.22 12.18 25.33 53.25 0.58 1.86 3.56 100 20 22.94 48.38 84.75 23.18 49.05 85.48 0.86 3.46 6.74 200 2 60.37 81.95 113.44 63.80 85.33 113.10 0.83 3.31 6.48 200 5 172.28 234.28 301.62 172.86 234.33 312.29 1.66 7.39 14.64 200 10 251.74 380.54 507.00 255.01 384.91 538.86 2.99 13.90 27.50 200 20 422.21 620.75 2758.04 436.15 638.97 879.57 6.24 28.09 55.82 Avg. 59.89 89.00 241.47 61.23 90.69 127.40 0.88 3.82 7.51 Table 6: Computational effort (seconds) required by the improvement heuristics on the testbeds with big instances 25