A Pomset-Based Model for Estimating Workcells' Setups in Assembly Sequence Planning

Valle Sevillano, Carmelo del; Toro Bonilla, Miguel; Ceballos Guerrero, Rafael; Aguilar, Jesús

Abstract

This paper presents a model based on pomsets (partially ordered multisets) for estimating the minimum number of setups in the workcells in Assembly Sequence Planning. This problem is focused through the minimization of the makespan (total assembly time) in a multirobot system. The planning model considers, apart from the durations and resources needed for the assembly tasks, the delays due to the setups in the workcells. An A* algorithm is used to meet the optimal solution. It uses the And/Or graph for the product to assemble, that corresponds to a compressed representation of all feasible assembly plans. Two basic admissible heuristic functions can be defined from relaxed models of the problem, considering the precedence constraints and the use of resources separately. The pomset-based model presented in this paper takes into account the precedence constraints in order to obtain a better estimation for the second heuristic function, so that the performance of the algorithm could be improved.

Full text

A Pomset-Based Model for Estimating Workcells' Setups in Assembly Sequence Planning Carmelo Del Valle, Miguel Toro, Rafael Ceballos, Jesús Aguilar Dept. Lenguajes y Sistemas Informáticos, Universidad de Sevilla, Avda. Reina Mercedes s/n, 41012 Sevilla, Spain {carmelo, mtoro, ceballos, aguilar}@lsi.us.es Abstract. This paper presents a model based on pomsets (partially ordered multisets) for estimating the minimum number of setups in the workcells in Assembly Sequence Planning. This problem is focused through the minimization of the makespan (total assembly time) in a multirobot system. The planning model considers, apart from the durations and resources needed for the assembly tasks, the delays due to the setups in the workcells. An A* algorithm is used to meet the optimal solution. It uses the And/Or graph for the product to assemble, that corresponds to a compressed representation of all feasible assembly plans. Two basic admissible heuristic functions can be defined from relaxed models of the problem, considering the precedence constraints and the use of resources separately. The pomset-based model presented in this paper takes into account the precedence constraints in order to obtain a better estimation for the second heuristic function, so that the performance of the algorithm could be improved. 1 Introduction Assembly planning is a very important problem in the manufacturing of products. It involves the identification, selection and sequencing of assembly operations, stated as their effects on the parts. The identification of assembly operations usually leads to the set of all feasible assembly plans. The number of them grows exponentially with the number of parts, and depends on other factors, such as how the single parts are interconnected in the whole assembly, i.e. the structure of the graph of connections. In fact, this problem has been proved to be NP-complete [1]. The identification of assembly tasks is carried out analyzing the graph of connections and taking into account the geometry of parts and the properties of contacts between parts [2] [3]. Two kinds of approaches have been used for searching the optimal assembly plan. One, the more qualitative, uses rules in order to eliminate assembly plans that includes difficult tasks or awkward intermediate subassemblies. Another approach, the more quantitative, uses an evaluation function that computes the merit of assembly plans. There are various of these proposals in [4]. The criterion followed in this work is the minimization of the total assembly time (makespan) in the execution of the plan in a multirobot system, supposed the estimations of the durations of each possible task as well as of the necessary resources to carry out them [5]. This approach allows using the results in different stages of the whole planning process, from the design of the product and of the manufacturing system, to the final execution of the assembly plan. The rest of the paper is organized as follows: Section 2 describes the problem of assembly sequence planning and the model used. Section 3 shows the proposed A* algorithm, as well as the two basic heuristics taken from relaxed models of the problem. The pomset-based model for estimating more accurately the minimum number of setups in the assembly machines is exposed in Section 5. Section 6 presents some of the results obtained, and some final remarks are made in the concluding section. 2 Assembly Sequence Planning The process of joining parts together to form a unit is known as assembly. An assembly plan is a set of partially ordered assembly tasks. Each task consists of joining a set of sub-assemblies to give rise to an ever larger sub-assembly. A sub-assembly is a group of parts having the property of being able to be assembled independently of other parts of the product. An assembly sequence is an ordered sequence of the assembly tasks satisfying all the ordering constraints. Each assembly plan corresponds to one or more assembly sequences. And/Or graphs have been used for a representation of the set of all feasible assembly plans for a product [6]. The Or nodes correspond to sub-assemblies, the top node coinciding with the whole assembly, and the leaf nodes with the individual parts. Each And node corresponds to the assembly task joining the sub-assemblies of its two final nodes producing the sub-assembly of its initial node. In the And/Or graph representation of assembly plans, an And/Or path whose top node is the And/Or graph top node and whose leaf nodes are the And/Or graph leaf nodes is associated to an assembly plan, and is referred to as an assembly tree. An important advantage of this representation, used in this work, is that the And/Or graph shows the independence of assembly tasks that can be executed in parallel. Figure 1 shows an example of this representation. And nodes are represented as hyperarcs. A B C D E A B C D A C D A B A C A D C D B E AB C D E Fig. 1. And/O r graph of product ABCDE. The problem is focused on searching an optimal assembly sequence, i.e. an ordering of an assembly plan (one of the And/Or trees of the And/Or graph). The evaluation of solutions implies a previous estimation of the durations and resources (robots, tools, fixtures…) needed for each assembly task in the And/Or graph. Another factor taken into account here, is the time necessary for changing tools in the robots, which is of the same order as the execution time of the assembly tasks and therefore cannot be disregarded as in Parts Manufacturing. () ,, cht R TT ′ ∆ will denote the time needed for installing the tool T in the robot R if the tool T' was previously installed. Notice that any change of configuration in the robots can be modeled in this way. 3 Algorithm description An algorithm based on the A* search [7] has been developed, which has two welldifferentiated parts: one of them studies the sequential execution of assembly tasks, and the other solves the parallel execution of assembly tasks (the representation through the And/Or graph allows a natural study of this stage). This is actually the most complex section, because the execution of tasks on one side of the global assembly is not independent of the rest, and can influence the execution of tasks in the other part of assembly. The heuristics showed below refer to this last part. Because of the set-up of the And/Or graph, the assembly problem can be studied, starting from the final situation and going towards the initial one. This way, we will solve the opposite problem, that of disassembly, but composed by assembly tasks, so that the solution of the original problem can be made reversing the solution obtained by the algorithm. Heuristic functions based on the execution of tasks taking only from the part of the tree below the node, and the time remaining for the use of tools and robots (supposing the minimum number of tool changes, in order to maintain the algorithm as A*) has been used in order to expand the minimum number of nodes and avoid redundant nodes. 3.1 Sequential Execution of Tasks An A* algorithm to search for the global assembly plan can be implemented in the following way. Beginning with an initial node whose state represents the complete assembly realization, and therefore corresponds to the root node of the And/Or graph (complete assembly), all its possible successors are generated, whose states will represent the execution at the end of the assembly process of the tasks corresponding to the And nodes coming from the root node of the And/Or graph. Two types of nodes may be generated, depending on the destination Or nodes of each chosen And node. If at least one of these Or nodes corresponds to an individual part, the assembly process will continue to be sequential, and the node resulting from the expansion may be treated as the initial node, where the node corresponding to the non-trivial sub-assembly will take the place of the root node. If, on the other hand, the application of the task starts from two sub-assemblies each with various parts, in the resulting plan (or plans in general) the task arrangement is not totally specified (various possible sequences exist for each assembly plan), or tasks may be carried out in parallel. There is also an interdependence amongst the sub-assemblies, because they potentially use the same set of resources. The treatment of this type of nodes has therefore to be undertaken in a different way from those corresponding to sequential task execution, and this will connect with the second part of this algorithm. The evaluation function used for the nodes generated in this part is () () () f ngnhn=+ (1) g(n) being the time accumulated in the execution of tasks corresponding to the state of node n, including the delays in the necessary tool changes and in the transportation of intermediate subassemblies, and h(n) being an optimistic estimation of the remaining time in which to complete the global process. (h(n) should be a lower bound of the remaining time for the algorithm to be A*.) Due to the fact that various different plans (and therefore different task sets which would complete the assembly process) may be reached from node n, a detailed study would be computationally costly, and therefore () 2 () log () 1h n durMin a n=⋅ +     (2) has been chosen, a(n) being the number of tasks necessary to complete the assembly plan, and durMin the minimum duration of tasks. As can be seen, it is also impossible to determine the minimum number of tool changes without a detailed study, and therefore when estimating h(n) it is assumed to be zero. All the assembly trees (task precedence trees) are obtained for the "parallel" nodes, and are studied separately. The function h(n) corresponding to each tree is defined in the following subsection. 3.2 Parallel Execution of Tasks The objective of this part of the algorithm is to determine the total minimum time for the execution of the precedence trees obtained in the previous section. In order to do this, an A* algorithm is again used. The nodes of the expansion tree now present partial information about the execution of the assembly process. Concretely, at each expansion step only one assembly task is introduced, and its processing time will affect only one of the workstations, the same state being retained by the other workstations. The state corresponding to a node of the expansion tree is represented by using the tasks available for introduction in the state of the next step, termed "candidates", and their earliest starting times, denoted est(Ji). At the same time, the last tool used is included for each robot, denoted lastTool(Rj), as well as the final time of use, denoted lastTime(Rj). The evaluation function for the nodes obtained by this algorithm is similar to (1), being now g(n) the largest of the earliest starting times of cand(n), the set of candidates, and the final times of the already finished in n without successors. The function h(n) must be an optimistic estimation of the time remaining, taking into account the slacks between g(n) and the different times describing the state of n. Two different heuristic functions have been defined in this work, taken from relaxed models of the problem in which some constraints have been disregarded. The heuristic function h1: precedence of tasks. It corresponds to an estimation of the time remaining if the interdependencies between different branches in the tree are not taken into account. It is looked at only in depth. It can be defined as follows: () () 11 () () max0, max ( ) (, ) iii cand n J hn hJ enJ ∈ =− (3) where ( , ) ( ) ( , ) ii enJ gn estnJ=− (4) () () 11 () () () max ( ) ,(),() iii JsucJ h J dur J h J J R J T J ∈ =+ +τ (5) () ) () () 1 () 1 (,,) max0,max ( ) ,(),() () iii JsucJ JRT h J J RJ TJ hJ ∈ τ= +τ − (6) In the above expressions, n is an expansion node, J is an assembly task, and e(n, J) is the existing time slack. R(J) and T(J) are the robot and tool necessary for the execution of task J, and dur(J) is its duration. τ(J, R, T) is the added delay, due to the fact that the tool T is being used by robot R in task J and successors, because of the necessary tool changes. The equation (6) defines τ(J, R, T) when R ≠ R(J). In the case R = R(J), τ(J, R, T) is defined as ∆cht(R, T(J), T) (that could be zero if T = T(J)). Notice that h1(J) does not depend on the expansion nodes, and thus allows one to calculate a lower bound prior to using the A* algorithm. The heuristic function h2: use of resources. It corresponds to an estimation of the time needed if only the remaining usage times of the tools in each robot are taken into account, further supposing the number of tool changes to be at a minimum. It can be defined as follows: () 22 () max (, ) (, ) ii robots hn hnR enR=− (7) where (, ) () (, )e n R g n lastTime n R=− (8) and h2(n, Ri) is the minimum time of use of robot Ri without considering the task precedence constraints. If each tool is associated with only one robot, the calculation of h2(n, R) is equivalent to the traveling salesman problem, when considering the tools not yet used and an initial node corresponding to the last used tool in the robot R: () 22 () (, ) ( , ) , () ji ij cht H R J cand n hnR hJT n R ∈∈  =+∆    ¦¦ (9) with h2(J, T) the remaining time of usage of tool T by task J and its successors. The term () ,() cht nR∑∆ refers to the time needed for the tool changes. In the usual case that tool changing times do not depend on the type of tool, it can be calculated easily: () ,() (,) () cht cht cht nRNnR R∑∆= ⋅∆ (10) where Ncht(n, R) is the number of tool changes needed in R for the remaining tasks for completing the assembly form n, and ∆cht(R) is the duration of a simple tool change in R. Without considering any precedence information, an in order to maintain the ad- missibility of the heuristic, it must be supposed that the remaining tools will be installed only once in the estimation of Ncht(n, R). 4 The Pomset-Based Model The heuristic h2 does not consider any information about precedence of tasks, and, in order to meet an admissible heuristic, it must be supposed that every tool will be installed once, so that the number of tool changes is minimized. The heuristic h3 is based on h2, but it estimates more accurately the number of tool changes. For that, a pomsetbased model is used that reflects some of the precedence constraints of the problem. Given a precedence tree of tasks, the tasks using the same machine must be done sequentially. For each sequence of tasks using the same machine, it can be defined a sequence of tools, in the same order that that of the tasks which use them. Because we are only interested in the tool changes, we must transform that sequence of tools in another one substituting consecutive repetitions of the same element for an instance of it. These sequences will be denoted as sequences of tools. The objective is to find, for each robot, the minimum number of times that each tool must be installed, but estimated in the more realistic way possible. Figure 2 shows a simple example: for the precedence tree of tasks (a), the precedence tree of usages of tools in the robot R1 is shown (b); in order to minimize the number of tool changes, T1 must be installed once, so that (c) represents the constraint precedence graph of tools, each node corresponding to possibly more than one consecutive usage of the tool. Finally, (d) represents the pomset1 corresponding to a simplified model of (c), maintaining only the precedence constraints referring to the tool in the top node. The data structure pomset was introduced by Pratt [8] in the specification of concurrent programs. An alignment is a sequence of the elements of the pomset satisfying the ordering constraints. In our pomset-based model, not all the possible alignments from the pomset will correspond to valid sequences of tools, because of the constraints that have been disregarded. For example, the pomset in Figure 2 (d) has an alignment {T2,T3,T2,T1}, which does not correspond to any possible sequences of tool formed from (c). However, this in not the main purpose, but the number of tool changes, which is related to the cardinality of the pomset. According to the previous comments, the pomset can be defined as a tuple ,<> BF , B being a multiset containing the same elements (and multiplicity) as the optimal sequence of tools taken from the precedence tree. On the other hand, F denotes the set of tools which can appear the first in any optimal sequence. Two basic operations are needed in the recursive definition of the pomsets (one for each robot) for a precedence tree. The first operation, denoted push, allows adding one element to the pomset, proceeding from the root node. The other operation, denoted merge, is about merging the pomsets from the subtrees. The pomset ,<> BF corresponding to a precedence tree whose root node is the task J and robot R, denoted P (J, R), is given by 1 pomset = partially ordered multiset. A multiset is a set in which the elements can be repeated. () { } { } () () () 11 12 12 (), () if () (,) (),( ,) if () {} () (), ( ,),( ,) if () {, } TJ TJ sucJ J R push T J J R suc J J R R J push T J merge J R J R suc J J J <> =∅  ≡=   ==  PP PP (11) if R is the robot used by J. If robot R is not the used by J, then the pomset is defined by () ( ) 11 12 12 if ( ) (,) ( ,) if () {} ( ) ( , ), ( , ) if ( ) { , } suc J JR J R sucJ J R RJ merge J R J R sucJ JJ ∅=∅   ≡=   ≠=  PP PP (12) The operation push is defined by () ,{ } if ,, {},{} if xx push x xx x <> ∈  <>≡ <>∉ S BF BF BF (13) that shows that the set of first elements must contain the element pushed only, and that and instance of this element must be added (operator , multiset additive union) when the element does no belong to the set of first elements of the original pomset, reflecting the corresponding additional change tool. The operation merge is defined by () () () 12 12 12 12 1212 12 ,, if , (, ) ,if , merge <>≠∅  ≡<> =∅   FF F BBDPP DPP PP BBFF DPP ∪ ∪∪ (14) where ()( )()() 12 1 2 12 21 ,,, ′′ ≡ FFF DPP FF DPP DPP∩∪ ∪ (15) and () { } , |#, #,()() ij i i j xx x ′≡∈ > F DPP F B B (16) The multiset union operator is defined taking the maximum multiplicity of each element, so that is the adequate operator for the resultant multiset from the merge of the pomsets. The resultant set of first elements is formed according to the concept of dominance. Figure 3 shows two cases. The symbol ⊗ represents the merge operator, J1 R1 T1 J2 R2 T4 J7 J8 J4 R2 T3 J3 R2 T3 J5 R1 T1 J6 R1 T3 J0 R1 T2 R1 T2 R2 T4 R1 –T2T3 T1 – –– T1 T2 T2 T1 T3 T2 T2 {T1,T2,T3} (pomset) (a) (b) (c) (d) Fig. 2. An example of a pomset from the model. and ⊕ is used for expressing the different possibilities we can obtain. In (a), we can obtain a pomset without increasing the number of instances of each element, because the element A in F1 has more instances in B1 than in B2, so we say that A is dominant. Moreover, B is not dominant because it cannot appear as first element in any optimal sequence of tools, i.e. without increasing the number of instances. In this situation, DF(P1,P2) is not empty, so we can determine the set of first elements without any problems. In case (b), A and B are not dominants, but the set of first elements cannot be empty. Notice that the optimal sequences can be taken from two different pomsets, in which the number of instances for A and B are different, expressing that the first element in an optimal sequence can be A or B, and depending of which is choosed, it has an additional instance. We say that there is an indetermination in the number of instance of A and B. The model proposed in this work makes a simplification about this aspect (see eq. (14)), so that the number of instances of A and B are not increased, and both appear as possible first element in an optimal sequence. This way, the resultant heuristic is admissible, but losing accuracy. On the other hand, if an element is present in the set of first elements in both pomsets, it must be present in the set of first elements in the resultant pomset. A last operation must be defined for the pomset structure, for obtaining the number of tool changes. This operation is denoted as ntrans, and for the model proposed in this work is defined as the number of elements of the multiset less one: () #(,)1 x ntrans x ∈ =− ∑ B PB (17) Finally, the new heuristic h3 is defined in the same way as h2 (eq. (9)), but in the calculation of () ,() cht nR∑∆ (eq. (10)), the term Ncht (n, R) is now estimated more accurately. If the candidate tasks in n are J1, ..., Jm, and T is the last tool used in R, () ( ) () () , , ( , ),..., ( , ) cht N n R ntrans push T merge J R J R=1m PP (18) 5 Results The algorithm has been tested in a variety of situations, considering different product structures (number of parts, number of connections between parts), different types of A { A, B, C } B { A, C } A { A, B, C } A { B, C } B { A, C } A { A, B, C } B { A, B, C } (a) (b) Fig. 3. An example of dominance. And/Or graphs (number of sub-assemblies, number of assembly tasks for each subassembly), and different assembly resources (number of robots, number of tools). The results in Tables 1-4 correspond to a hypothetical product of 30 parts, with 396 Or nodes and 764 And nodes in the And/Or graph. The number of linear sequences is about 1021. The tables show the effect of having more or less resources for assembling the product in the performance of the algorithm. The results refer to 10 different combinations of durations and resources for assembly tasks. The heuristic functions defined present two different effects in calculating h(n). The estimation made from h1 is due to the most unfavorable candidate task. In the other hand, h2 and h3 shows an additive effect, because of the uses of robots by all candidate tasks. Therefore, two new heuristic functions can be defined from the com- Table 1. Results for 2 machines and 2 tools/machine Nodes visited Time (ms) Heuristic Ave Max Min Ave Max Min N-Pr N-F % Error h1 41492 89189 2520 19429 30590 180 4 6 0,990 h2 9316 42775 32 1422 6420 0 5 0 0,000 h3 617 3019 32 176 870 0 2 0 0,000 max(h1, h2) 16385 71585 32 4291 30050 0 4 1 0,248 max(h1, h3) 3422 30506 32 3257 31470 0 1 1 0,248 Table 2. Results for 2 machines and 4 tools/machine Nodes visited Time (ms) Heuristic Ave Max Min Ave Max Min N-Pr N-F % Error h1 40093 56108 3020 25025 30930 710 2 8 2,648 h2 5311 19398 267 790 4230 50 1 0 0,000 h3 1458 6120 32 198 930 0 1 0 0,000 max(h1, h2) 5078 19009 387 1143 4450 60 1 0 0,000 max(h1, h3) 1303 4805 32 418 1870 0 1 0 0,000 Table 3. Results for 4 machines and 2 tools/machine Nodes visited Time (ms) Heuristic Ave Max Min Ave Max Min N-Pr N-F % Error h1 16905 85540 32 2357 11700 0 1 0 0,000 h2 2751 7195 32 263 710 0 2 0 0,000 h3 1781 7011 32 533 2030 0 3 0 0,000 max(h1, h2) 804 2098 32 99 220 0 2 0 0,000 max(h1, h3) 794 2098 32 148 330 0 2 0 0,000 Table 4. Results for 4 machines and 4 tools/machine. Nodes visited Time (ms) Heuristic Ave Max Min Ave Max Min N-Pr N-F % Error h1 22697 93376 32 6084 30530 0 4 1 0,302 h2 1808 5907 128 197 660 0 1 0 0,000 h3 1072 5014 119 396 2260 0 1 0 0,000 max(h1, h2) 1765 5907 32 278 980 0 2 0 0,000 max(h1, h3) 1062 5014 119 396 2260 0 1 0 0,000